Safety
Overview
Methods/Equipment
Medium,Temperature, gauges
Precautions/Considerationss
100

JS5

Job Safety Five

100

All newly constructed ___, ___, and transmission lines before placing in service.

Mains, services

100

Preferred on pipe with design less than 60 psig

What is Pneumatic testing?

100

Test mediums must be___, ___, ___ or ___.

air, NG, inert gas or water

100

________________ on the pipe during testing is Prohibited

Working

200

Stand clear

Dead ends, test heads, hoses under pressure

200

Preferred testing medium for low pressure

What is Air?

200

Uses water as test medium

Hydrostatic testing

200

Distribution systems use___

air or inert gas

200

Not required for testing purposes

Backfill

300

PPE

Personal Protective Equipment

300

preferred test medium for high and transmission lines.

H2O

300

Two types of equipment used in pressure testing are:

Pressure gauge

Pressure test recorder

300

It is important that temperature of pipeline being tested ____ 

Constant

300

after placing into service...

Soap test all fittings and joints

400

Recognize and React

All AOCs

400

All pretested pipe installed must_____

test info legibly written on the segment

400

MAOP

Maximum Allowable Operating Pressure

400

WG pressure test gauge

Kuhlman gauge and Spring gauge/ bottle test kit

400

10" and larger

dead ends must weld 

500

Properly secure _____ & test heads & _____ while under pressure.

dead ends hoses

500

Pressure test components other than pipe, _____

insulating joints and fittings

500

Pipelines are tested at _____ times MOAP

1.5

500

Pressure testing operations must be surpvised by ___________ 

Qualified personnel

500

Overnight or longer between testing

Retest prior to gassing