Approximately how many square feet of P-105 pedestrian rated concrete sidewalk are present in this section of the project?
3,441 SF
How many square feet consists of P-301 vehicular rated decomposed granite?
9,200 SF
Approximately how many lineal feet of W-106 seat wall are present in this section of the project?
334 LF
How many cubic yards of concrete are required to pour the P-103 vehicular rated concrete sidewalk?
402 CY
Approximately how many cubic yards of P-302 decomposed granite will be required in this section?
115 CY
Approximately how many square feet will consist of P-702 rubberized asphalt?
10,052 SF
Assuming a cost of $120/CY of concrete, what would be the material cost for the P-108 concrete paving?
$48,900
Assuming a cost of $50/CY of decomposed granite, what would be the total material cost for all decomposed granite at this section of the project?
$14,250
Approximately how many cubic yards of concrete will be required to pour the W-106 seat wall?
87 CY