What document demonstrates that a Chapter has formally approved or supported a road project?
Chapter Resolution
Which utility provider is commonly associated with water and electrical infrastructure on the Navajo Nation?
NTUA
What does ROW stand for?
Right-of-Way
What does EA stand for?
Environmental Assessment
A road project requires removing trees within the construction limits. What permit should the team investigate?
Forestry Permit
A road improvement project conflicts with fiber-optic infrastructure. Which CURE utility category should be checked?
Telecommunications
What does TAA stand for?
Tribal Access Authorization
What does BRCF stand for?
Biological Resources Clearance Form
Before geotechnical crews begin drilling boreholes, what clearance document may be required?
Drilling Permit
What are the five utility categories listed in the CURE checklist?
Water, Sewer, Electric, Telecommunications, Gas
What does TCE stand for?
Temporary Construction Easement
What does CRCF stand for?
Cultural Resources Clearance Form
A proposed roadway crosses an area used by livestock permittees. What clearance item should be reviewed?
Grazing Leases
A waterline conflicts with a proposed drainage structure. What should the project team document?
The utility conflict, provider coordination, and proposed resolution or relocation
A proposed road improvement affects an individually allotted parcel. Which CURE ROW category should the team review?
Allotments
What environmental review category is commonly abbreviated CatEx?
Categorical Exclusion
Name three types of land-use or agency clearances identified in the CURE checklist.
Any three: Grazing Leases, Homesite Leases, Chapter Resolutions, Farm Boards, Forestry Permits, ADOT Permit, or the added Drilling Permits
A utility provider identifies a conflict but has not agreed to relocate its facilities. Is utility coordination complete?
No. The conflict remains unresolved and requires follow-up and documentation
A bridge project needs temporary construction space beyond its permanent ROW. What documentation should the team investigate?
Temporary Construction Easement documentation, including applicable legal descriptions, plats, and consent or authorization
A road project may affect a wash or other waterway. Which two Clean Water Act permitting sections should the project team evaluate?
Sections 401 and 404