Regulatory
Technical
Monitoring
Earthing / Grounding
100

What is the maximum Project size possible under Net Metering in Maharashtra 

999 Kwp

100

What is long form of MPP?

Maximum Power Point

100

What is the maximum capacity of GCRT as per MNRE guidelines for "Manual Monitoring"

5 Kw

100

What should be the depth of earth pit

Type & depth depends on soil resistance. It should  be less than 2 Ohms

200

What are the net metering registration charges for 7 Kw installation ?

Rs 1000/- + GST = Rs 1180/-

200

What is the recommended height of LA

To cover the complete PV module area based on the data sheet of LA

200

What are the reports expected from On line monitoring portal

Daily / monthly / Yearly Generation reports

200

How many earthing pits are required for GCRT setup

2 sets of grounding : LA + Electrical Earth : Numbers, depth & type depends on the soil resistance 

300

What is the maximum capacity of GCRT Solar PV you can put for a domestic consumer with monthly 500 KWH consumption and sanction load of 1.5 Kw / 1PH

1.5 Kw/ 1Ph

300

What will happen if the string voltage is less than the MPP range of inverter

Inverter will not start

300

What is the ideal frequency to check portal in case of normal functioning of GCRT

Once a day

300

How many MINIMUM parallel paths are recommended for grounding  

Min 2

400

What are the conditions for sanction of Solar PV system .

1. GCRT not exceeding sanctioned load
2. Not exceeding 40% of DT capacity

400

What is the best combination of modules in series for a given MPP range of inverter 

Check the MPP graphs at different voltages in the data sheet & select the optimum voltage  

400

How many days data can be accumulated on the inverter in case of communication failure

Depends on memory of inverter which will vary from brand to brand - It is typically 1 Month +

400

Do you need isolated earthing for LA

Yes. It has to be separate 

500

What is the validity of GCRT agreement with DISCOM

20 Yrs

500

What is the name of technique used for shadow compensation 

Optimizing Technique

500

What are features you should look for in On line Monitoring

Instantaneous -> power,  AC & DC - Voltage & Current
Reports -> Daily / monthly / Yearly reports
Error - > Error Log

500

What should be the size of earth conductor

Material and size of earth conductor should be capable of handling twice the fault current 