In September 2020, this GE software version was installed on certain older DEC volume-environment servers.
What is GE version 3.10 SPI?
This term means the target point when the program is prepared for a production release and the applicable criteria have been satisified.
What is Solution Ready?
This application serves as the ADMS program's main system of record for team workload.
What is Jira?
This event establishes the program vision and planning context before teams finalize their PI Plans
What is the Program Vision and PI Planning Context meeting?
This type of ADMS resource performs work across jurisdictions rather than being assigned to only one.
What is Shared Services team member?
Older files dated June 2026 of this year were still found on Raleigh environment servers during a later infrastructure review
What is 2020?
This structured tracker brings criteria, owners, and readiness evidence together before a release is declared ready.
What is the Solution Readiness Tracker, or SRT?
These four levels form the ADMS program's Jira data structure.
What are Capabilities, Objectives, Epics, and Stories?
This workshop reviews unresolved alignment, risks, impediments, and dependencies before commitment.
What is the PI Problem-Solving Workshop?
This informal program principle says participants may leave a meeting after informing the facilitator if they do not see value in attending
What is the Law of Two Feet?
This release family appeared in Duke's newer DEC volume servers associated with the 2023 implementation.
What is ADMS 3.16?
This 2025 jurisdictional upgrade included detailed planning, analysis, design activity, leadership engagement, and storm-scenario workshops
What is the DEF ADMS upgrade?
ADMS planning follows this scaled framework on a quarterly Program Increment cadence.
What is SAFe, or Scaled Agile Framework?
This ceremony concludes the planning sequence and confirms the program's PI commitment.
What is the PI Commitment Ceremony?
In 2025, program meetings moved toward these views to ensure the appropriate participants and audiences were included.
What are focused jurisdictional views and/or meetings?
On April 23, 2024, the GE release history added this ADMS version.
What is ADMS 16.7.0?
Before a 2025 production decision, the team used two temporary cutovers, business and technical validations, critical-defect checks, rollback criteria, and a vote.
What is a go-live readiness process?
These four words describe the required information placed in program meeting invitations.
What are Purpose, Process, People, and Payoff?
At the program level, teams make commitments at this Jira work-item level rather than the story level
What is the Epic level?
This new 2025 function was established to create more structure around vendor relationships, partner performance, statements of work, invoice approvals, and milestone acceptance.
What is the Vendor Management Office or VMO?
These four successive ADMS versions were documented between September and November 2024
What are 16.11.0, 16.12.0, 16.13.0, and 16.14.0?
These two jurisdictions were aligned to the same ADMS 16.15 patch level during a 2025 production-upgrade discussion.
What are DEP and DEM (Midwest)?
This four-letter technique is used to disposition uncertainty as Resolved, Owned, Accepted, or Mitigated.
What is ROAM?
A PI commitment has these two parts: agreeing to do everything possible to meet the Epic and doing this immediately if delivery becomes jeopardized.
What is escalating so action(s) can be taken?
Name the sequence of the three program events that typically converts planning work into a formal PI commitment before Jira Data Health was added as a separate event.
What are Vision and Planning Context, Problem-Solving Workshop, and Commitment Ceremony?