COPs 1
COPs 2
COPs 3
COPs 4
COPs 5
100

Before putting a piece of equipment or a process into service after a change, this must be signed off first?

What is: PSSR

100

To find the definitions for the two classifications of hot work, you would find them in this document.

What is: Hot Work and Atmospheric Testing COP

100

If you wanted to know what the 3 different colors of tags mean on scaffolding, you could look here?

What is: Working at Heights COP

100

This is where you would look to find the minimum requirements to enter a space with limited access and suspicious atmosphere.

What is: Confined Space Entry COP

100

Lifting with two or more cranes or over live process piping

What is: Critical Lift

200

A modification or variation of a component of an existing design, asset, process, piece of equipment, control system or facility one of these is required.

What is: MOC

200

Control logic overridden or a PSV temporarily taken out of service.

What is: Process Inhibits Override

200

A document that determines distances for hand exposure requirements around pipelines

What is: Ground Disturbance COP

200

Use this document to determine the responsibilities of the Performing Authority during a critical lift.

What is: Lifting and Rigging COP

200

Here is where you would find the requirements for a “long term isolation” or an “alternative isolation”?

What is: Isolation of Hazardous Energy COP

300

The distance between ground locate stakes

What is: 5m

300

How soon should you report a pipeline leak?

What is: Immediately

300

Hydrate training should be completed by all individuals according to competency profiles identified in what program?

What is: CMDS

300

A document to be posted at vessel entrance before going inside.

What is: Confined Space Permit

300

The part of the fall protection equipment that supports the body in event of a fall.

What is: Full Body Harness

400

An isloation with a single locked block valve

What is: Alternative isolation

400

The Completions team roll up in their boogie van and want to work on your well. You determine you will shut the well in, what document is required before work can proceed?

What is: Wellsite handover

400

A part of the workers PPE that stops the worker from falling and does not allow the worker to fall further

What is: Fall Arresting Device

400

In addition to a CSE permit, what training must the worker have before entering the space.

What is: Confined Space Entry ticket

400

If a drug test is required for reasonable cause or post incident, within how many hours of discovery must the test be completed?

What is: 32 hours

500

The disicipine or role with authority to approve a single block valve isolation.

What is: Professional Engineer

500

A mixture of water and hydrocarbon gas molecules that crystalize under certain conditions of temperature and pressure.

What is: Hydrate

500

The average distance we drive with Canlin fleet vehicles in a year

What is: ~4,000,000 kms

500

In Alberta, you can downgrade a space below confined space.  A key determining factor that differentiates the space classification is the atmospheric hazard. What is this type of space called?

What is: Restricted Space

500

Operations has a producing lease and construction kicks the door open and wants to install some new equipment in the middle of the lease. (Assuming the site stays running) what document is required

What is: Simultaneous Operation

M