Other
Competent Person
Soil
Protective Systems
Hazardous Conditions
100

What is the difference between a sounding bar and a probing bar?

What is: insulated handle on the probing bar to protect against electrical shock
100

If a trench is greater than _____ feet deep, a registered professional engineer must design the system.

What is 20

100

True or False: In a trench with multiple soil types, the soil classification will always be the strongest type. 

What is false

100

Shoring removal will begin at, and progress from, the ______ of the excavation.


What is the bottom

100

Equipment, materials and trench spoils shall not be stored within ___ feet of the edge of the trench.

What is 2

200

A _________ is an example of a portable device used for shielding.

What is a Trench (Build-A) Box

200

A competent person is responsible for determining the soil classification based on what two tests?

What are visual and manual

200

A soil cannot be classified as Type A if _________, ___________, or _________.

a) it is fissured b) subject to vibration c) previously disturbed.

200

If a trench is between 5 ft. and 20 ft. deep the competent person may select from Sloping and Benching, _______ and Shielding as acceptable protective measures.

What is SHORING

200

Excavation daily inspections should look for 1)_____ 2)______ 3)______ and 4)_______.

What is 1) shoring requirements 2) water accumulation 3) undermining 4) sloughing

300

Protective systems shall be inspected by the manufacturer at what frequency?

What is annually

300

Under what conditions must a Competent Person inspect an excavation?

What are: Daily, throughout the shift, and after conditions change (rainstorm) or due to other hazardous condition.

300

Name 3 types of manual soil analysis.

What is 1) plasticity (cohesiveness) 2)dry strength 3) thumb penetration

300

Shields shall extend  _____ above the vertical top of the trench or excavation face.

What is 18 inches

300

An oxygen deficient atmosphere contains less than ____ % oxygen.

What is 19.5

400

PPE on every jobsite includes _________, _______, and ________.

What are: 1) hard hats 2) steel toed boots 3) hi-vis vest

400

A competent person as defined by OSHA is one who is ___________ of identifying existing hazards and one who has the ___________ to take prompt measures to abate the hazards.

What is CAPABLE and AUTHORITY

400

Type B soil descriptions are 1)______ 2)______

3)______

What is 1) silt 2) sandy loam 3) medium clay

400

A soil Type C excavation of less than 20 ft deep can be sloped at a _to_ (horizontal to vertical) or ___ degrees.

What is 1 1/2 to 1

What is 34 degrees

400

A stairway, ladder, or ramp will be located in excavations 4 feet or more in depth every ____ lateral feet.

What is 25

500

Employees performing copper pulls must wear ASTM approved _____ KV high voltage insulating gloves with leather over-gloves when handling the cable or pipe.

What is 20 KV

500

A competent person may determine a trench less than 4 feet may require a protective system if there are signs of 1)______ 2)_______or  3)________.

What are 1) water 2) vibrations 3) previous disruption.

500

Type C can be described as: 1)______ 2)_______

3)_______ 4)________

What is 1) gravel 2) loamy sand 3) soft clay 4) previous disturbed

500

A soil Type B excavation of less than 20 ft deep can be sloped at a _to_ (horizontal to vertical) or ___ degree

What is 1:1

What is 45 degrees

500

What is the stop-work criterion for hydrocarbons on the gas meter?

What is 10 ppm for 1 minute