Vocab
Project Time Management
More Vocab
100

What is a sequence activity?

a) the process of identifying and documenting relations among project activities

b)the order in which you will do the activities 

c) not necessary to use lead or lag time 

d) all of the above 

a) the process of identifying and documenting relations among project activities

100

What is project time management? 

a) staying on track with your project work

b) when you use your time wisely 

c) the component of overall project management where a timeline is developed and analyzed 

d) all of the above

d) all of the above

100

__________ dependency is based on knowledge of best practices within a particular application area

a)plan 

b)application

c)solo

d)discretionary

d)discretionary

200

What does the activity list include? 

a) all the activities you will do in the project 

b) little to no detail 

c) the activity identifier and scope of work

d)what is not required to be done

c) the activity identifier and scope of work

200

The most powerful word in using time management is _______. 

a) hello

b)no

c)demand

d)multiple 

b)no

200

The rolling wave plan:

a) the idea of not planning in waves 

b)milestones will not be set during this time 

c)the process of planning in waves as the project proceeds

d)none of the above 

c)the process of planning in waves as the project proceeds

300

The _______ chart illustrates a project schedule

a) Activity

b)Gantt

c) Participation 

d) Pie 

b)Gantt

300

Why should you always start a project with a plan? 

a)to help others around you 

b)manage your time correctly

c)to be late to the project 

d)leave early for personal reasons 

b)manage your time correctly

300

What contains descriptive information useful in detailing activities? 

a)worksheets

b)blueprints 

c)brains

d)templates

d)templates

400

Which method is a visual representation technique that depicts  the activities involved in a project?

a) start to finish

b)start to start 

c)mandatory

d) none of the above

d) none of the above

400

Which situation should you dedicate your time to?

a)going to meet with your clients

b)following the original plans of the project 

c)going to meetings about a different project 

d)taking as lunch break 

a)going to meet with your clients

400

Dependencies which involve a relationship between project activities and non project activities:

a)internal 

b)external

c)employees 

d) mandatory

b)external