chapter 1
chapter 2
chapter 3
chapter 4
chapter 5
100

what are the 3 dependencies?

 (ex. apollo 13 had examples of these)

mandatory,  external, and  discretionary

100

 what is Lag

A modification of a logical relationship that directs a delay in the

successor activity. For example, in a finish to start dependency with a

ten day lag, the successor activity cannot start until ten days after the

predecessor activity has finished.

100

what are the three point estimates

most likely, optimist,pesstimistic

100

Reserve Analysis is what


Duration estimates may include contingency reserves, (sometimes

referred to as time reserves or buffers) into the overall project

schedule to account for schedule uncertainty.

100

Project schedule

An output of a schedule model that presents linked activities with planned

dates, durations, milestones, and resources.

200

what are these examples of

Justification

Product scope description

Acceptance criteria

Deliverable 

Project conclusions

Constraints

Assumptions

project scope statement

200

 what is a Gantt Chart



Graphic display of schedule related information. In the typical

bar-chart, schedule activities or WBS components are listed down the

left side of the chart, dates are shown across the top, and activity

durations are shown as date-place horizontal bars.

200

 what is Lead


A modification of a logical relationship that allows an acceleration of

the successor activity. For example, in a finish to start dependency

with a ten day lead, the successor activity can start ten days before

the predecessor activity has finished. A negative lead is equivalent to

a positive lag.

200

Critical Path Method

A schedule network analysis technique used to determine the

amount of scheduling flexibility (the amount of float) on various

logical network paths in the project schedule network, and to

determine the minimum total project duration.

200

Bar charts

A graphic display of schedule-related information. In the typical bar chart, schedule activities or

work breakdown structure components are listed down the left side of the chart, dates are

shown across the top, and activity durations are shown as date-placed horizontal bars. See also

Gantt chart.

300

what is Used to analyze the information needed to develop the project scope statement and Judgment/ expertise is applied to any technical details.

Expert Judgment

300

what is a Sequence Activities

The process of identifying and documenting relations among the

project activities.

300

what has the capability to help plan, organize, and manage resource pools

and develop resource elements

Project Management Software

300

Critical Chain Method

A schedule network analysis technique that modifies the project

schedule to account for limited resources.

300

Project Schedule network diagram

A graphical representation of the logical relationships among the project schedule activities.

400

what is a Analogous Estimating

A high level estimate used to include program evaluation review techniques (PERT)

estimations.

400

 what is a Milestone



A significant point or event in a project.

400

what is Bottom-Up Estimating



When an activity cannot be estimated with a reasonable degree of

confidence, the work within the activity is decomposed into more

detail. The resource needs are estimated. These estimates are then

aggregated into a total quantity for each of the activity’s resources.

Activities may or may not have dependencies, this pattern of

resource usage is reflected and documented in the estimated

requirements of the activities.

400

Resource Leveling

Any form of schedule network analysis in which scheduling decisions

(start and finish dates) are driven by resource constraints (e.g. limited

resource availability or difficult to manage changes in resource

availability levels).

400

Stakeholders?

 persons or organizations who are actively involved in the project

or whose interest may be positively or negatively affected by the performance or

completion of the project.

500

 what is Parametric Estimating

Used to estimate the quantity of work and productivity rate per unit of work.

500

 what is Rolling wave planning

A form of progressive elaboration planning where the work to be

accomplished in the near term is planned in detail and future work is

planned at a higher level of the WBS.

500

 what is Precedence Diagramming Method (PDM)

A schedule network diagramming technique in which schedule

activities are represented by boxes (or nodes). Schedule activities are

graphically linked by one or more logical relationships to show the

sequence in which the activities are to be performed.

500

Schedule Compression

Shortening the project schedule duration without reducing the

project scope.

500

what is a WBS

work breakdown structure

M
e
n
u