Who is can make any necessary changes to a contract?
Contracting Officer
What is the driving force of all elements in the Base Camp Life Cycle?
Command & Control
What is the equation for Free Float (FF)?
FF = TF - IF
What type of bridge is considered both Tactical and Support?
REBs
When calculating Cover Requirements in the Aggregate Pavement Design Process, what is the equation for B?
B = Y - A
Rule of Thumb #1: 2" or less, delete and add to Base Layer (A); 3" or more, use minimum allowable thickness
What products are closely related and tied together, used during contracting operations?
Performance Work Statement (PWS) and Statement of Work (SOW)
What are the four principles of Base Camps?
Scalability, Sustainability, Standardization, Survivability
What are the Project Components?
Time, Money, Scope
What Bridge Classification Method is used as a temporary measure, under emergency conditions, and requires no calculations? This method is only applicable on certain types of bridges.
Rapid Field Classification Booklet
Compacted CBR
What are the two levels of Quality Control?
Unit Quality Control Program and Project Quality Control Plan
What classification would be used on a Base Camp with a duration 'up to 5 years'?
Temporary
What is the definition of Project Management?
The application of knowledge, skills, and resources to accomplish activities that are intended to achieve a specific goal.
For a single-lane bridge, how would you draw a dual classification for both Wheeled and Tracked vehicles?
page 182 in battle book
What category would a M1A1 (weighing 63 tons) be in? (when determining the traffic category in Step 3 of Aggregate Pavement Design Process)
Category VII
When utilizing the basic cost model, what Adjustment Factor is almost always used during Step 5?
1.05 (Fire and Other Alarm Systems)
What classification of Base Camps includes considerations of 'tenant units, host nation personnel, and the approximate population expected'?
Size
What is Interfering Float (IF)?
The float which if an activity is delayed into, will cause a delay in one or more activities.
What are the five Gap Crossing Priorities?
1. Existing Bridges 2. Detours/Bypasses 3. Repairs/Reinforcement 4. Tactical Bridges 5. Line of Communication (LOC) Bridges
What are the levels of Pavement Selection in correct order?
(top-bottom)
Asphalt, Base, Subbase, Select Material, Compacted Subgrade
Where do you find the Area Cost Factor (Step 3) when utilizing the Basic Cost Model?
Pricing Table Guide Table 4-1
What are the five Levels of Service Standards?
Pre-establishment, Basic, Expanded, Enhanced, and Transfer or Closure
What is the resource estimating formula?
Quantity x Work Rate = Standard Effort / Efficiency = Troop Effort / Crew Size = Duration
What are the components of Non-Standard Fixed Bridges?
Deck, Railing, Abutment, Wingwall, Pier, Stringer
Label all Road Nomenclature.
through-cut, side-hill cut, shoulder, culvert, fill, traveled way, surface or wearing course, base, subgrade