Scope
Tools and Techniques
Out puts and processes
100

What is the main document used to define and authorize a project or phase?

Project Charter

100

What technique involves using a series of images or illustrations to show a mockup of what a program would look like once a user is using it?

What is Storyboarding 

100

Which process involves progressively elaborating the work into greater detail as more information becomes available, often used in adaptive life cycles?

What is the Requirements Traceability Matrix?

200

This document outlines how the project scope will be defined, developed, monitored, controlled, and verified?

Scope Management Plan

200

Which data gathering technique allows stakeholders to generate and gather many ideas, usually allowing all stakeholders to document their ideas?

Brainstorming

200

This process is critical for breaking down project deliverables into smaller, more manageable components, which are then used to estimate cost, time, and resource needs.

What is Decomposition

300

What process involves subdividing the project deliverables and project work into smaller, more manageable components?

What is Create Work Breakdown Structure (WBS)

300

What is a one-time method used to quickly define requirements, solve differences, and build trust among stakeholders?

What is Facilitated Workshops

300

This technique involves a panel of experts providing input anonymously to avoid the influence of dominant personalities and is often used in scope management.

What is the Delphi Technique

400

What is The primary output of the "Define Scope" process?

What is Project Scope Statement

400

Which process ensures that project deliverables meet the quality requirements before they are formally accepted by the customer or sponsor?

What is Validate Scope

400

This process ensures that only the approved scope of work is included in the project and that any deviations are formally controlled and documented.

What is Control Scope?

500

In the process of collecting requirements, which tool and technique involves using formal or informal discussions to discover information from stakeholders?

What are interviews

500

The document that shows the requirements to be collected, analyzed, documented, and managed, and is part of the project management plan?

What is Requirements Management Plan

500

This tool and technique gathers data from stakeholders using questionnaires or surveys to understand their needs and expectations.

What are Questionnaires and Surveys?