HVAC
GENERATOR
FIRE & LIFE SAEFTY
ELECTRICAL
GENERAL KNOWLEDGE
100

WHAT COOLING EQUIPMENT DO WE USE TO COOL THE DATA HALL? If you don't know the model, then the acronym can suffice

CRAC DSE 265

XDM-300

CDU-1350

100

WHAT TYPE OF FUEL DO WE USE FOR OUR GENERATORS?

RED DYED DIESEL (OFF ROAD DIESEL)


100

WHAT ARE THE 2 CONDITIONS THAT MUST BE MET TO ACTIVATE THE PRE-ACTION SYSTEM?

CROSS DETECTION (2 SMOKE HEADS IN A SINGLE ZONE) AND LOSS OF AIR PRESSURE

100

WHAT IS YOUR ELECTRICAL PPE

EYE PROTECTION/FACE SHIELD

RATED GLOVES

SAFETY SHOES

ARC FLASH SUIT

100

WHAT IS DIGITAL REALTY'S CORE VALUES?

CUSTOMERS, EXCELLENCE, TALENT, TEAMWORK AND SUCCESS.

200

HOW MANY HUMIDIFIERS ARE IN EACH CRAC GALLERY, HOW MANY PER SUITE?

2 PER CRAC GALLERY, 4 PER SUITE

200

WHEN IS THE OZONE SEASON, AND WITHIN WHAT TIME FRAME CAN WE NOT DO NON-EMERGENCY RUNS?


MAY 1ST - SEPTEMBER 30TH

NO NONEMERGENCY RUNS FROM 7AM - 5PM



200

WHAT ARE THE MONITORED 3 GAUGES ON A PRE-ACTION CABINET? IN ORDER FROM TOP TO BOTTOM

SYSTEM AIR PRESSURE, PRIMING PRESSURE, SYSTEM WATER PRESSURE

200

WHAT IS A CLOSED TRANSITION?

WHAT IS: "MAKE-BEFORE-BREAK" (NEVER LOSE POWER)

THE CONTACTS FOR THE ALTERNATE SOURCE ARE CLOSED BEFORE THE CONTACTS OF THE ORIGINAL SOURCE ARE OPENED.

200

WHAT SOFTWARES DO WE USE FOR MAINTENANCE TRACKING, AND WHAT ARE THE FORMS/DOCS WE USE FOR EACH?

INSITE AND MCIM. INCIDENT REPORT (IR) OR CHANGE REQUEST (MOP ACCEPTABLE)

300

WHAT IS REFRIGERANT AND WHAT TYPE DO WE USE?

A CHEMICAL COMPOUND THAT ABSORBS HEAT THROUGH AIR AND IS CAPABLE OF TRANSITIONING FROM LIQUID TO VAPOR AND BACK AGAIN.

 R410A


300

WHEN A GENERATOR IS RUNNING (LOADED OR UNLOADED), WHAT COMPONENTS MUST BE OPEN TO ENSURE PROPER OPERATION AND SAEFTY & WHY ARE THEY OPEN?

DAMPERS FOR VENTILATION AND AIR FLOW TO COOL THE GEN DURING OPERATION AND THE DOORS IN CASE OF EMERGENCIES OR DAMPER FAILURE

300

WHAT ARE THE MAJOR COMPONENTS OF A PRE-ACTION?

Flapper/Deluge valve

Water Supply

Dry pipe

Priming Pressure Line

Priming Pressure Gauge

Water Supply Pressure Gauge

Release Valve

300

WHAT TYPES OF LOADS ARE FED FROM THE MECHANICAL PANELS?

CRACS (COMPUTER ROOM AIR CONDITIONING)

ACCUS (AIR COOLED CONDENSING UNIT)

300

WHEN DO WE NEED TO CALL THE BUILDING OUT FOR ALL SIGNALS AND WHO DO WE CALL?

HOT WORK, HIGH RISK WORK, FIRE SYSTEM TESTING (ANY OF THE 3)

WE CALL (BFPE) BALTIMORE FIRE PROTECTION AND EQUIPMENT 

400

1 REFRIDGERNT TON IS EQUAL TO = ____ KW

3.517 OR 3.52

400

WHAT ARE THE PARAMETERS OF OUR GENERATORS?

1800RPM

60Hz

480V


400

WHAT ARE THE COMPRESSORS USED IN THE PRE-ACTION CABINET AND THEIR PURPOSE?

NITROGEN TO SUPPLY NITROGEN IN THE PIPES AND AIR TO COMPENSATE IF THERE IS A LOW PSI AND CONTROL WATER FLOW IF NEEDED TO DISCHARGE

400

WHAT IS AN AUTOMATIC TRANSFER SWITCH (ATS).

AN ELECTRICAL SWITCH THAT SWITCHES THE LOAD BETWEEN TWO SOURCES. (MAIN UTILITY AND GEN BACKUP)

DETECTS WHEN THERE IS A POWER FAILURE IN THE MAIN UTILITY AND TRANSFERS THE LOAD TO BACKUP UTILITY (GEN). 

SWITCHES THE LOAD BACK TO MAIN UTILITY ONCE THE MAIN UTILITY IS RESTORED. 

400

WHAT ARE THE EVENT ESCALATION TYPES AND COURSE OF ACTION FOR EACH?

GREEN - INCIDENT REPORT (IR) AND CHANGE REQUEST (CR)

YELLOW - MANAGER ENGINEERING OPERATIONS (MEO)/MANAGER ON DUTY (MOD), GLOBAL COMMAND CENTER (GCC) 

RED - SAME AS YELLOW

500

WHAT IS THE 4 STAGES OF THE REFRIGERATION CYCLE.

COMPRESSOR - INCREASES PRESSURE. (HIGH PRESSURE, HIGH TEMP VAPOR)

CONDENSER (SUB COOLING) - REJECTS HEAT. 

EXPANSION VALVE (EEV) - REMOVES PRESSURE. (LOW PRESSURE, LOW TEMP, VAPOR LIQUID MIX)

EVAPORATOR - ABSORBS HEAT. (LOW PRESSURE, HIGH TEMP, VAPOR)



500

DESCRIBE THE 4 STROKE DIESEL ENGINE COMPONENTS THAT CAUSE THE ENGINE TO RUN.

INTAKE, COMPRESSION, COMBUSTION, EXHAUST

500

WHAT ARE THE FIRST 2 SECTIONS OF PIPING WHEN YOU ENTER THE WATER ENTRY ROOM CALLED?

BACK FLOW PREVENTER AND FIRE DEPARTMENT CONNECTIONS

500

EXPLAIN WHAT DISTRIBUTED REDUNDANCY IS IN A 4 TO MAKE 3 SYSTEM, IN A 6MW SUITE.

4 UPS WITH 1MW (1000KW) CAPACITY MAX EACH ARE INSTALLED TO DELIVER THE CAPACITY OF 3. 

IN A 4 TO MAKE 3 SYSTEM ALL 4 UPS ARE SET TO ONLY USE 75% (750KW) LOAD OF CAPACITY IN CASE 1 UPS FAILS. IF 1 UPS FAILS THE REMAINING 3 UPS WILL BE DISTRIBUTED 25% OF THE LOAD EACH FROM THE FAILED UPS, TAKING THE REMAINING 3 UPS TO THEIR MAX CAPACITY (1MW/1000KW).

500

WHAT ARE THE BADGE COLORS AND WHO ARE THEY DESIGNATED FOR

YELLOW - CUSTOMERS

BLUE - EMPLOYEES / VENDORS

GREEN - VISTOR (DAILY/EXTENDED)

RED - ESCORTED