Top Terms
Formidable Formulas
Critical Components
PM Parlance
Andrew's Adages
100

Costs that have been invested into the project (and cannot be recouped)

What is Sunk Cost

100

This formula calculates the number of channels needed based on the number of project stakeholders

What is Communication Channels?

n*(n-1) / 2

100

The four components of SWOT analysis

What are Strengths, Weaknesses, Opportunities, and Threats?

100

Planned procrastination that results in unnecessary stress and diminished safety margins -- and reminiscent of collegiate life

What is Student Syndrome?

100

According to Andrew, you should not do this before taking the PMP exam

1. Drink heavily

2. Sedate yourself 

3. Stay up all night

200

This term refers to doing extra work that is not in the project scope

What is Gold Plating?

200

The amount of time you can delay an activity without delaying the project end date, calculated using late/early start and finish

What is Float?

Late Start minus Early Start or Late Finish minus Early Finish 

(LS - ES) or (LF - EF)

200

The three types of procurement/ contract strategies

What are Fixed Price (Lump Sum), Cost-Reimbursable, and Time & Materials?
200

A common tool in conflict management (and real life!), this PM term refers to saying or doing things that cannot hurt you, now or in the future. 

What is Self-Protection?

200

According to Andrew, wearing this color will bring you good luck on exam day!

What is Blue?

300

The longest path from start to finish (without any loops or overlaps)

What is the Critical Path?

300

The equation for expected activity duration using a weighted average of three estimates (Optimistic, Pessimistic, and Realistic)

What is the Three Point Estimate (PERT):

(Optimistic + (4 x Realistic) + Pessimistic) / 6

300

When closing your project, ensure these three elements are included in your final report.

1. Summary (what took place in the project?)

2. Success (was the project a success?)

3. Variation (any variations in the baselines?)

300

Runners, take your mark...

This PM term refers to the handing off of work from one team to another, often resulting in wasted time if the second team is not ready.

What is Dropped Baton?

300

According to Andrew, this project aspect is always present, and it is the job of the PM to identify and respond to it over the project lifecycle.

What is Risk?

400

Unauthorized work added to the scope

What is Scope Creep?

400

Critical to Earned Value Management, this calculation tells you the amount of money worth of work you actually did on the project

What is Earned Value?

EV = Actual % Complete X Budget at Completion

400

A stakeholder has identified the need for a change request! These three steps must happen next.

1. A written change request submitted to PM

2. The PM assesses the change impact, considers options

3. The change request is submitted to Change Control Board for approval

400

You may be guilty of this PM term if you are always under-promising and over-delivering

What is sandbagging?

400

According to Andrew, successful projects (and relationships) depend on these two things.

What are Communication and Engagement?

500

This paired term refers to the overlap as well as the delay between first and second activities

What is Leads and Lags

500

This culminative Earned Value Management equation indexes the performance that needs to be met to complete the project within budget.

What is To-Complete Performance Index (TCPI)?

TCPI = (BAC - EV) / (BAC - AC)

BAC = Budget at Completion; EV= Earned Value; AC = Actual Cost 

500

The five rungs of Tuckman's Ladder 

hint: they rhyme

What are forming, storming, norming, performing, and adjourning?

500

Not to be confused with the neurodegenerative disease, this law states that 'work expands to fill the time available for its completion'. 

What is Parkinson's Law?

500

In a ______ organization, the PM has little to no control, while in a ______ organization, the PM very high or total control.

What are Functional and Projectized?

M
e
n
u