100

These people are responsible for monitoring direct charges to charge numbers

Who are CAMs?

100

These are expenses that are not directly attributable to a specific project but are necessary for running the overall business.

What are Indirect Costs?

100

This is the earliest point performance can be taken for material

The actual receipt of the material items

200

These are costs recorded in the EV cost system as actuals, even though the expenses have not yet been incurred in reality.

What are Estimated Actuals

200

This should be done if an incorrect charge is made to a CAM's charge number

Use the approved company procedure to process a labor or material cost transfer in a timely manner

200

this is the latest point performance for material can be taken

the point of consumption

300

What is the purpose of estimated actuals?

to ensure ACWP occurs in the same reporting period BCWP is taken

300

These reports show CAMs information about who is charging to their charge numbers

What are labor reports?

300

Can performance be taken on material that has been cancelled?

No