the frequency of reimbursement requests
Every 6 months
the number of awarded BEAD grant projects
What is 22?
# of Days Colorado BBO has to pay an approved invoice
What is 45 days ?
What is 14 days?
% completion when site visits occur
50% and 100% complete (Will also accept site visits based on risk level of project)
% of award is eligible for the Final Deliverable 10 reimbursement
What is 10%?
this gates access to deliverables 2-6.
What is NEPA approval?
lookback date
When is December 5, 2024?
Colorado Project with the Highest Match Requirement
What is Mountain Parks? (6.7 MILLI!)
The required minimum match for BEAD deployment projects
What is 25%?
Deliverable 1
What are NEPA Project Areas submitted and NTIA Approval? (will accept environmental package submitted and approved)
Number of BEAD grant projects in MS
What is 5?
The number of awarded BEAD grant projects in LA
What is one?
Required frequency of reimbursement requests
This milestone triggers the Notice to Proceed and enables construction.
What is EHP/NEPA approval?
Number of days Subgrantee has to submit reimbursement requests after the Performance Period Ends
What is 90 days?
Date for eligible pre-award costs
When is January 7, 2026?
This Deliverable is gated by NEPA Approval
What is Deliverable 3?
These must be provided to support reimbursement at higher completion milestones.
What are invoice details or budgets vs. actuals?
the milestone number that starts construction
What is Milestone 3?
This risk involves costs incurred before the contract effective date.
What are non-reimbursable or non-allowable pre-award costs? ( will accept variations of this )
What is Ten Years?
the deliverable that relates to project mobilization
What is Deliverable 3?
Number of days following period of performance end date to submit Final Performance (Technical Report)
The number of days before construction required for public awareness/notice
What is 30 days?
the name of our largest budgeted award project area
What is Ozark Border?
The cure period for a breach of contract before remedies may be exercised (number of days)
What is 30 days?
name one of the remedies OPB can impose for non-compliance
What is withholding payments, requiring corrective action plans, recoupment of funds, denying reimbursement claims, terminating the award, or prohibiting future grant participation?
the % of total award reimbursable before NEPA approval
What is approximately 16.6%
Each phase will be treated as a "__________"
What is a sub-project?