Uncertainty
100

5D BIM Modeling represents ..

Cost

100

The first video I showed you in the lab

Laborers playing music on site

100

The name Monte Carlo refers to the game found in (comes from)

Monte carlo casino

200

A software that helps in modelling building information and 3D models

Revit, ArchiCAD, ..

200

A reference for calculating construction cost estimation

RS Means

200

One type of uncertainty is

Variation-variability/ foreseen uncertainty/ unforeseen uncertainty/ chaos

300

LOD in BIM is..

Level of development/detail

300

The name of the sticky notes activity during lab 1 (concept it represents)

Collaborative planning

300

The distribution used in PERT analysis for ACTIVITY duration

Beta distribution

400

Several building systems were developed and applied to the constructed projects starting in the .. (years)

1980’s

400

Location in MS project to define resources, units available, standard rate, etc

Resource sheet

400

an uncertain/ unexpected event that, if occurs, has an effect on your project objectives, such as time, cost, scope or quality/ Consequence of uncertainty is.

RISK

500

When a BIM model is projected onto the real project site to show how he virtual model overlays into the real surrounding, it is called..

Augmented reality

500

The cost chart we drew in lab 4 included the cost variance between … (two measures)

Budget at completion (BAC) and Estimate at completion (EAC)

500

Critical chain project management CCPM is based on theory….

Theory of constraints (TOC)