5D BIM Modeling represents ..
Cost
The first video I showed you in the lab
Laborers playing music on site
The name Monte Carlo refers to the game found in (comes from)
Monte carlo casino
A software that helps in modelling building information and 3D models
Revit, ArchiCAD, ..
A reference for calculating construction cost estimation
RS Means
One type of uncertainty is
Variation-variability/ foreseen uncertainty/ unforeseen uncertainty/ chaos
LOD in BIM is..
Level of development/detail
The name of the sticky notes activity during lab 1 (concept it represents)
Collaborative planning
The distribution used in PERT analysis for ACTIVITY duration
Beta distribution
Several building systems were developed and applied to the constructed projects starting in the .. (years)
1980’s
Location in MS project to define resources, units available, standard rate, etc
Resource sheet
an uncertain/ unexpected event that, if occurs, has an effect on your project objectives, such as time, cost, scope or quality/ Consequence of uncertainty is.
RISK
When a BIM model is projected onto the real project site to show how he virtual model overlays into the real surrounding, it is called..
Augmented reality
The cost chart we drew in lab 4 included the cost variance between … (two measures)
Budget at completion (BAC) and Estimate at completion (EAC)
Critical chain project management CCPM is based on theory….
Theory of constraints (TOC)