These are a part of the Close Out Requirements, and provide exactly how the project was actually built.
What are the Record Documents?
300
Rights, roles, relationships & responsibilities of the contractual parties.
What are the General Conditions of the Contract?
300
This POTUS signed into law the OSH Act of 1970?
Who is Richard Nixon?
400
This delivery method has all contractual parties on the same team, from Day 1 thru the end of the project.
What is Design Build (or IPD)?
400
The cost of doing business.
What is General Overhead?
400
During construction, this is anything that is "submitted".
What is a Submittal?
400
Owner, A/E, Contractor & Subcontractor
Who are the contractual parties with responsibilities specified in AIA A201-General Conditions
400
This 1st sheet of a drawing set provides a 3d sketch of the project, TOC for the drawing set, professional titles, and other specific project information.
What is the Cover Sheet or Title Sheet/ Title Page?
500
In this method, the CM does not self-perform any construction work on the project.
What is Agency CM?
500
An estimate is just that; and estimate of projects costs; whereas this item is an "contractual" estimate; we contractually agree to build the project for this price.
What is a Bid?
500
Product brochures and data, samples, and these fabrication drawings are a part of certain product submittal requirements.
What Shop Drawings?
500
Specified description of relationship between the Drawings & the Project manual or Specs
What are "complimentary".
500
Part 1-General
Part 2-Products
Part 3-Executuion
What are the 3 parts of the CSI 3 Part SectionFormat