Fundamentals
Math
Risk
TLA
Miscellaneous
100

This is a temporary endeavor undertaken to create a unique product, service, or result.

What is a Project?

100

Find the float of this activity:

ES=7

LS=11

EF=14

LF=18

4

100

What are you doing if you as the PM are; Conducting risk management planning, identification, analysis, response planning, and controlling risk on a project.

Risk Management

100

What is SWOT?

Strengths, Weaknesses, Opportunities, Threats Analysis.

100

If you are doing the following, what are you doing?

Interviews
Focus groups
Facilitated workshops
Group creativity techniques
Group decision-making techniques
Questionnaires and surveys
Observations
Prototypes
Benchmarking
Context diagrams
Document analysis

Collecting Requirements

200

Identify the 5 process groups

What is Initiating, Planning, Executing, Monitoring & Controlling, and  Closing.

200

On a given project; earned value (EV) is $30,000; actual cost (AC) is $35,000; and planned value (PV) is $28,000. What is the schedule performance index (SPI)?
                         

1.07

200

A mobile device manufacturer is halfway through prototyping a new product when the supplier who provides one of the raw materials used to manufacture their device casings declares bankruptcy and goes out of business. The team had not foreseen this problem during project planning. 

Which of the following best describes a process that may not have been performed comprehensively in this scenario?

What Is Identify Risks?

200

What is VAC?

VAC= Variance at Competion

200

What is not the job of a PM?

- The wrenching

- Determining if a project is feasible

300

An organization decides to group several related software development projects. Managing them together provides benefits like shared resources and coordinated timelines, which wouldn’t be possible if they were handled individually. What is this coordinated group of projects called?

What is a program?

300

On a given project; earned value (EV) is $250,000; actual cost (AC) is $215,000; and planned value (PV) is $300,000. What is the schedule variance (SV)?

-$50,000

300

What kind of chart is commonly used for risk analysis?

Risk Matrix or Stoplight Diagram

300

What is EEF?

Enterprise environmental factors

300

Dennis has just been assigned to an Agile project due to his leadership abilities from previous projects. He is known to focus on his team's growth, learning, development, autonomy, and well-being. Which leadership style does this best represent?

What is Servant Leader

400

During a project, the client continuously requests new features that were not part of the original agreement, without allowing for changes to the timeline or budget.

What is Scope Creep?

400

What is the CPI of this project?

  • EV= 36,244.19

  • AC= 505,014.23

  • PV=8,758.23

0.0718

400

Your communications plan lacks escalation paths. What risk does this create?

Miscommunication

400

What are OPAs?

Organizational Process Assets

400

Placing many or all of the most active project team members in the same physical location to enhance their ability to perform as a team.

What is Colocation

500

A team is building a new type of satellite where the technology is unprovem and requirements are expected to evolve as they learn more. Which project life cycle approach would be most appropriate.

What is adaptive?

500

You are on a project with the following stats, What is your VAC?

  • PV:$25,000

  • EV:$30,000

  • AC:$29,000

  • BAC:$100,000

$3288.20 OR $3333

500

During the execution of a project, a significant risk event occurs. The pre-approved risk response strategy is implemented, but it proves ineffective, causing a 2-day delay and overspending on the contingency budget. The risk is now closed. What should the project manager do first?

Update the risk register with details of the event and the failed response.

500

What is PERT?


Program evaluation and review technique

500

What is the formula used to find the number of communication channels needed for a project?

N(N+1)/2