100

What form needs to be submitted daily for Force Account work?

Form 316, "Daily Report of Force Account Work"

100

When does the contractor have to pay subcontractors to follow prompt payment requirements?

Within 10 days of TxDOT paying the Prime for the work done. Retainage may be held.

100

What type of projects require FHWA Area Engineer approval for change orders?

Projects of Division Interest (PoDI) depended on the FHWA agreement. 

100

What is one thing that should be done if unanticipated hazardous materials are found in the project? 

Suspend work in the impacted area and consider a time extension. 

Relocate the contractor to avoid/minimize construction downtime. 

Contact District ENV coordinator to evaluate and determine if special action is needed.

Secure the area for worker and public safety. 

Notify the AE and DCO

100

What are Supplemental Agreements used for?

Assign the contract from one entity to another. 

Change the legal name of the contractor. 

Settle disputes involving a Surety. 

200

Starting with May 2020 letting, which form should be used as the preconstruction agenda?

Form 2796

200

How often should contractor performance evaluations be conducted?

Interim evaluations - Annually

Final evaluation - Before running the Final Estimate

200

What types of projects does the DBE program apply to?

All highway improvement contracts involving federal funds that include a DBE goal. 

200

What is one exception for the Buy America requirement? 

The cost doesn't exceed $2,500 or 0.1% of the total contract cost (whichever is greater)

The material is temporarily installed. 

The contract was awarded based on an alternate bid item for foreign source steel or iron product. 

200

How often should labor interviews be conducted?

3 employee labor interviews should be conducted for each project per quarter. 

300

When is a Texas Ethics Commission (TEC) Form 1295 required?

Whenever there is a CO with a value greater or equal to $1 million OR

If the cumulative COs increase the contract amount by $1 million or more. 

300

What is the max amount of work that can be subcontracted? 

70% of the total original contract amount. 

300

How often should the Local Government Project Procedures (LGPP) Qualification Program be completed?

Once every 3 years. 

300

What type of materials are eligible for Material on Hand (MOH) payments?

Nonperishable items with an invoice greater than $1,000. 

300

What occurs when a claim is filed by the contractor?

CST - Claims Section reviews the claim and provides a complete report to the contractor, District, and Contract Claims Committee (CCC). The CCC ultimately decides the proposed disposition of the claim. 

400

What is Form 599 used for and how should it be filed? 

Traffic Control Devices Inspection Checklist

File it separate from the project files and do not disclose. Do not make any copies. 

400

When should Priority 1 and Priority 2 TCP deficiencies be corrected? 

Priority 1 - Immediately 

Priority 2 - Within 7 days

400

Where can you find the list of posters required on the project site bulletin boards?

CCAM Chapter 17 or FHWA website.

400

When may material be purchased from the contractor?

If the restocking fee is greater than the cost of the materials to be purchased. &

Contractor suitably stores/stockpiles material

Materials meet contract requirements when State takes ownership

400

What should be done when defaulting a contractor with a performance bond?

Always coordinate the default process with CST. Construction Support will coordinate the Takeover Agreement with the Surety for Construction projects. 

500

When should Form 2146 be used?

Form 2146 can be used as a guide when creating change orders. It includes a checklist, reason code list, and Third-party notification sheet. 

500

What are the requirements for the Contractor's superintendent?

Competent English-speaking

Experienced with the work and capable of reading and understanding the contract. 

Available at all times and able to receive instructions and act for the contractor. 

500

Which FHWA form needs to be physically incorporated into each construction contract, subcontracts, and lower-tier subcontracts with federal-aid funds?

Form FHWA-1273, "Required Contract Provisions - Federal-Aid Construction Contracts"

500

What document should be used to determine the appropriate testing procedures for materials?

Guide Schedule of Sampling and Testing for Design-Bid-Build Projects (The Guide Schedule). 
500

When is a TDLR inspection required?

When the project has $50,000 worth of pedestrian elements. If that value is exceeded through COs ensure to have the RAS review and register the project plans prior to completion. 