This is Clune's Original SOV for "0420 - Masonry"
What is $17,995?
This is the Clune "SOV Change" value for "0420 - Masonry"
What is $6,833?
This is the "Work Completed This Period" for "0420 - Masonry"
What is $11,349?
This is the "This Period Retainage" for "0420 - Masonry"
What is $1,134.90?
This is the actual payment amount for A. Horn Inc. Masonry this month
What is $10,214.10?
This is Clune's current SOV for "1014 - Signage"
What is $35,476?
This is the Clune "SOV Change" value for "0241 - Demolition"
What is $825?
This is the "Work Completed This Period" for "0968 - Carpet"
What is $0?
This is the "Total Retainage" for "0420 - Masonry"
What is $2,296.40?
This is the date for which this Pay Application is "completed through"
What is February 28th, 2023?
This is Sub-Surface Sign's current contract value
What is $6,273?
This is the total "Change Order" value for Milburn LLC
What is $4,250?
This is the "Work Completed This Period" for "1014 - Signage"
This is the standard retainage percentage on all subcontracts and POs
What is 10%?
This is Clune's "Balance To Finish, Including Retainage" after this Pay Application
What is $881,078.44?
This is the current SOV for "9700 - Insurance"
What is $26,458?
This is Clune's NET Change Order value on the project
What is $17,060?
This is the "Work Completed This Period" for "9700 - Insurance"
What is -$1,477?
This is the "Total Retainage" for the entire project
What is $115,890.78?
This is the Pay Application number
What is Pay Application #5?
This is Clune Construction's current contract value
What is $2,256,576?
This is the value of Clune Change Orders approved "this month"
What is $0?
This is the "Work Completed This Period" for the entire project
What is $346,796.93?
This is the "This Period Retainage" for the entire project
What is $11,691.89?
This is the "Percent Complete" for "Temp Controls" line item within FE Moran's HVAC invoice?
What is 85%?