Preconstruction Activities
Construction Observation
Administrative Procedures & Protocols
Project Closeout & Evaluation
CSI Specifications
100

Which delivery system is popular with owners?

What is design-bid-build?

100
What document is issued at the beginning of construction?

What is, the owner issuing a notice to proceed

100

A minor change in the work

What is a change that does not involve a change in the contract sum or time

100

Who performs the substantial completion inspection?

What is the architect

100

Div. 01

General Requirements

200

IPD stands for?

What is, Integrated Project delivery

200

Difference between a change order and a construction change directive?

A change order involves a change in prices, schedule or scope and all three parties (owner, contractor and architect) must agree. A Construction change directive involves the same changes but only the owner and architect have to agree

200
Who pays for additional inspection or testing?

If the work fails inspection the contractor pays, if it passes the owner pays. Additional testing and inspection is typically required by the architect when suspect work arises.

200

What document marks the end of the construction process?

What is the issuance of the certificate of occupancy

200

Div. 09 

Finishes

300
Three components that make up the procurement documents?

What is project manual, contract drawings and Addenda

300

What submittals does the contractor provide to the architect? Name at least 3

What is action submittals, shop drawings, coordinate drawings, product data, samples

300

Difference between quality assurance and quality control in construction?

QA: the procedures for guarding against defects and deficiencies before and during execution of the work. QC: the procedures for evaluating completed activities and elements of the work

300

Difference between substantial and final completion?

Substantial: occurs when the project is sufficiently complete according to the contract documents to allow the owner to use.

Final completion: project is complete according to the contract documents. Date of final payment marks date of final completion.

300

Div. 03

Concrete

400

Difference between and alternate and a substitution 

Alternates provide the Owner with a choice between different products or can define the addition or deletion of a portion of the Work.  A substitution is a change in products, materials, equipment, and methods of construction from those required by the Contract Documents and proposed by Contractor

400

Clear width of a ramp?

What is 36"

400

Who serves as the IDM (the Initial Decision Maker)

The architect, unless otherwise noted in the contract

400

Purpose of Evidence Based Design

Per AHPP, EBD is a design process that leverages best practices and current knowledge in order to solve a problem or answer a specific question through a rigorous process that resolves design issues with evidence.

400

Div. 22

Plumbing

500

What is the difference between Construction Manager as Adviser and Construction Manager as Constructor?

CMa advises the owner on constructability but assumes no risk. CMc typically uses a GMP which puts the CM at risk for cost overruns.
500

AIA document for sustainable project

What is the A201-2007 SP, B101-2007 SP and E204-2017

500

Which of the following are legally binding: mediation, arbitration, and/ or litigation?

What is arbitration and litigation

500

What information does the commissioning plan include? Name at least 2

Construction checklists

Commissioning schedule and protocols

Required documentation

Testing and inspection plans

List of systems or other elements to be commissions

Responsibilities of team members

500

Div. 26

Electrical

M
e
n
u