What is the waiting period, for a normal VA811 ticket, from the time you call in to the time when you can perform work?
100
Respect the Marks
What does the R stand for?
100
Excavate Carefully
What does the "E" stand for?
200
Allow required time for marking.
What does the "A" stand for?
200
All days except Saturdays, Sundays and legal and state holidays
Define "Working Days"
200
"Non-working days"
What should you not include in the waiting period?
200
Sewer
What does green paint represent?
200
2
You can not utilize mechanized equipment within ___ feet of a marked utility.
300
Respect the marks.
What does the "R" stand for?
300
15 working days
How long is your notification valid?
300
Confirmed completion of a positive response
What situation prevents you from having to wait the required 48 hours?
300
Approximate horizontal location
What do the markings represent?
300
Visual evidence, Knowledge, Faded Marks
What is clear evidence?
400
Excavate carefully
What does the "E" stand for?
400
1
How many miles must your excavation NOT exceed?
400
7 am, the next working day after your call
When does the waiting period begin?
400
Protect and Preserve
You should ______ & ______ the markings from the time the excavation begins until markings are no longer required for the proper and safe excavation near the utility lines.
400
proper support
Provide ______ _______ for underground utility lines during excavation activities.
500
Acronym
The C.A.R.E message is an abbreviation or one of these?
500
Name
Number
Address
email
Name two things you must supply the call center, while giving notice?
500
Monday
If I called in a ticket today, when would it be completed so that excavation could occur?
500
Reclaimed water, Irrigation and Slurry lines
What does purple paint stand for?
500
10'
What is the Advisory Committee's policy for maximum depth (number of feet)?