Planned scope of the project.
What is to open an airport with a conventional tug-and-cart baggage system?
Planned completion date.
When is October 1993?
Planned Cost for the Project.
The variance of the scope of the project.
What is attempted to proceed with a technology sophisticated automated system airport wide with known risk?
The city the project took place in.
What is Denver?
Actual scope of the project.
What is an airport opened with system only for United’s outbound luggage, with tug-and-cart system for concourse A and C not airport wide?
Actual completion date.
When is February 1995?
Actual cost of the project.
What is more than $290m?
Time Variance.
What is 16 months?
The system this project intended to design for the airport.
What is an automated baggage claim?
An issue with the scope.
What are workers knew of the issues the automated systems provided, but continued anyways?
First date the project what pushed back too.
What is October 1994?
Caused the cost variance.
Cost Variance.
What is ~$95m?
Names of the presenters.
Who are Dean, Nick, Chan, Trai, and Jocelyn