Scope
Time
Cost
Variance
Background
100

Planned scope of the project.

What is to open an airport with a conventional tug-and-cart baggage system?



100

Planned completion date.

When is October 1993?



100

Planned Cost for the Project.

What is $195m?
100

The variance of the scope of the project.

What is attempted to proceed with a technology sophisticated automated system airport wide with known risk?



100

The city the project took place in.

What is Denver?

200

Actual scope of the project.

What is an airport opened with system only for United’s outbound luggage, with tug-and-cart system for concourse A and C not airport wide?



200

Actual completion date.

When is February 1995?



200

Actual cost of the project.

What is more than $290m?

200

Time Variance.

What is 16 months?

200

The system this project intended to design for the airport.

What is an automated baggage claim?

300

An issue with the scope.

What are workers knew of the issues the automated systems provided, but continued anyways?

300

First date the project what pushed back too.

What is October 1994?

300

Caused the cost variance.

What is chaining the plans, modifying, and changing orders.
300

Cost Variance.

What is ~$95m?

300

Names of the presenters.

Who are Dean, Nick, Chan, Trai, and Jocelyn