Deliver that Ish
Bid that Ish
Bond that Ish
Read that Ish
Alphabet Ish
100

This project delivery method requires the design to be substantially complete before contractors competitively bid the work.  

Design-Bid-Build

100

This is the contractor’s decision whether to pursue a project.

Go/No-Go Decision

100

This bond guarantees a bidder will honor its bid.

Bid Bond

100

This document tells bidders how to prepare and submit a bid.

Instructions to Bidders

100

RFI

Request for Information

200

This project delivery method uses a single entity responsible for both designing and constructing the project.

What is Design-Build?

200

This form of detailed estimating produces a price based on estimated quantities and specified unit rates for those quantities.

Unit Price Estimate

200

This bond protects against unpaid suppliers and subcontractors.

Payment Bond

200

Written technical requirements included as part of the bid package or contract. This may include material type. 

Specifications

200

A/E

Architech and Engineer

300

This project delivery method typically uses a Guaranteed Maximum Price.

CMAR

300

Money included in an estimate to address uncertainty.

Contingency

300

This term describes the maximum amount of work a contractor can be supported for by a surety.

Bonding Capacity

300

This formal question is submitted when bid documents are unclear.

RFI

300

GMP

Guaranteed Maximum Price

400

This collaborative delivery model shares risks and incentives among parties.

Integrated Project Delivery

400

The process of extracting quantities from drawings.

Quantity Takeoff

400

This bond guarantees the contractor will perform the work in accordance with the contract

What is a Performance Bond

400

This term describes a bidder whose proposal complies with all bidding requirements.

Responsive Bid

400

CMAR

Construction Manager At Risk

500

In this contract structure the owner holds contracts with multiple prime contractors.

Separate Contracts

500

The amount added to cover overhead and profit.

What is Markup?

500

What are the parties engaged involved in a bond?

Who are Principal, Surety and Contractor?

500

This document revises bidding requirements after the original bid package is issued.  

Addendum

500

WBS

Work Breakdown Structure

M
e
n
u