Principals of Project Development
Project Development Blueprint
Ins & Outs of EPC
Life Cycle Risk and Insurance
Financial Modeling
Financing Structures
100

What are two of the four development domains?

  • Technical
  • Commercial
  • Social
  • Financial
100

What is the name of the process of retiring “project” risks to achieve a physical operating asset with positive economics?

Project Development

100

Is the following statement True or False:

More Engineering equals Better Defined Scope equals Lower EPC Bids.

TRUE

100

Is the following statement True or False:

Effective risk allocation means assigning residual risks to the parties best able to assume them, considering capacity, control, and creditworthiness.


TRUE

100

What is one metric commonly used to evaluate the financial viability of an infrastructure project?

IRR, MOIC

100

Is the following statement True or False:

It is best to set up a special purpose vehicle to insulate each project.

TRUE

200

What kind of firms or entities are the most likely ultimate owners of infrastructure projects following their demonstration of steady cash flows?

Pension Funds, Insurance Firms

200

How many phases are there in the project development process?

Five (5)

200

What is one common mistake Developers often make after the EPC price comes in too high?

  • go out for more bidding
  • change technology
  • cut contingency
  • self-perform EPC themselves
  • cut scope required for performance and quality
200

Is the following statement True or False: Technology performance insurance can cover construction delays and cost overruns.

FALSE


200

Is the following statement True or False: The IRR metric considers the time value of money

TRUE

200

Is the following statement True or False:

FOAK projects are typically financed by non-recourse debt.

FALSE

300

What is the definition of infrastructure?

Interrelated system notes and links

300

In the technical domain, name one final deliverable that creates asset value. 

Anyone of site studies completed, FEED design, or permits secured

300

What are two of the four most common EPC contract structures?

  • Fixed Price (or Lump Sum)
  • Cost Plus Fee
  • Guaranteed Maximum Price
  • Unit Price
300

Is the following statement True or False: Developers who engage insurers early can design coverage that better meets investor and lender needs.

TRUE

300

Is the following statement True or False: You should not assume anything in a financial model

FALSE

300

What is one major risk that will reduce Developer’s perceived credibility and increase fundraising difficulty?

insufficient project documents

poorly negotiated commercial agreements

high project costs

major project scope gaps

400

What are the three "things" that Ken would like you to leave Dev U remembering?

  • Goal
  • Approach
  • Perspective
400

What are the two primary uses of capital during development, and which one do financiers value more?

3rd party* and soft costs

400

What are the three Front End Loading (FEL) stages that occur before EPC bidding?

Conceptual Design, Preliminary Engineering, Project Feasibility

400

 Is the following statement True or False: Underwriters evaluating first-of-a-kind technologies look only at proven operating history and ignore third-party validation or testing.

FALSE


400

Is the following statement True or False: Techno-economic calculations should be omitted from the financial model.

TRUE

400

What is one way a Sponsor can be compensated for performing its role in a project finance structure?

  • Development fee (milestones / earnouts)
  • AUM fee
  • Royalty
  • Profits interests (carry)
  • Disposition of interests
500

What is the fundamental objective of project development?

Producing documents as fast and as cheap as possible until deciding to either stop or continue funding

500

What is the name of the role that oversees the overall project execution strategy and is usually your first development team hire?

Project Executive

500

What is the rule of thumb for the range of total cost of engineering when expressed as a percent of total project CAPEX?

Anywhere between 4 to 10%

500

Name one thing underwriters look for when considering technology performance insurance.

Reliable test data, independent third-party validation, or achievement of project milestones

500

Is the following statement True or False: The higher the IRR, the higher the MOIC


FALSE

500

What is one major risk that Offtake agreements typically transfer to Developers?

1.    Off-taker credit and performance

2.    Project performance guarantee

3.    Deadlines and off-taker approvals

4.    Project collateral support requirements


M
e
n
u