Name at least one type of the estimation
Story points, ideal hours/days, T-short sizing, Fibonacci, Power of 2, dogs
What are the main Scrum ceremonies?
Sprint planning; Requirement elicitation; Daily scrum; Sprint review; Sprint retrospective
What is the level where we plan Stories, tasks, commitment?
Iteration planning
What is the unit of measurement of tasks in planning poker?
Fibonacci, including 0
Name at least 3 key Scrum metrics
Team capacity; Team velocity; Escaped defects; Sprint burndown; Epic and Release Burndown
Name at least one measure for estimation
Traditional measures of size (Lines of Code, Function Points); Agile measures of size (Story points, Ideal days/hours, T-shirt sizes, Cup-size, Fibonacci, Power of 2); #NoEstimate
Why standups should take place always in one place & at the same time?
To reduce complexity
What is the level where we plan Iterations, team capacity, stories, priority, size, estimates, the definition of done?
Release planning
When the Tech Lead opens his card?
Together with everyone
What Story Point does mean?
How hard is it? (Complexity) & How big is it? (Efforts)
Who is responsible for facilitation in team events in the SCRUM team?
Scrum master
What is the level where we plan a date, theme/feature set, objective, development approach?
Product roadmap
How much time can take to estimate one story?
As much as needed (the discussion process continues until a consensus is reached).
What could be estimated on the Project?
Budget, time, resourses (triangle)
What is the goal of planning A and B?
A: What will be done during the iteration
B: How the planned work will be done
What is the level where we plan: What, who, why, when, constraints, assumptions?
Product vision
What is the role of the Scrum master on the Planning session?
Facilitation