What is the voltage typically used in Level One Charging?
120 V AC
What is the key factor that affects installation costs when placing EV Chargers on a site?
Proximity to the power source
What is the primary connector used for Level 1 and Level 2 in North America?
SAE J1772
What percentage of new cars sold globally is expected to be electric by 2040?
More than 50%
What is the typical voltage for Level 2 EV Charging Stations?
208-240 V AC
How many miles of range does a Level 2 Charger Typically provide per hour?
10-30 miles
When assessing a site for EV Charging, what should be done if trenching is required?
Evaluate the distance, ground conditions, and potential obstacles
What feature of networked EV Charging stations allows remote monitoring and control?
Cloud-based connectivity
What government initiative aims to install 500,000 EV chargers across the U.S.?
The Infrastructure Investment and Jobs Act
What California Building Code requires a percentage of parking spaces to be EV Capable?
CalGreen - New Construction Building Codes
What type of charging is primarily used for for long-distance travel?
DC Fast or Level 3
Why is it important to check the cellular connectivity when assessing a site for EV Charging?
Our stations are SIM/Cellular based and our drivers need a smart phone to activate a charge
What feature helps prevent cables from becoming tripping hazards or getting damaged?
Retractable Cable Management
Which region leads the global market in electric vehicle adoption?
Europe and China
What does the National Electric Code (NEC) Article 625 cover in terms of EV Charging?
Installation and inspection of EV Supply Equipment (EVSE)
Which EV Charging level typically uses CHAdeMO and CCs Connectors?
DC Fast or Level 3
What site characteristics should be evaluated to ensure ADA compliance?
the proximity of the stations to accessible paths, curb cutouts, and the height of the stations.
What type of charging station provides energy monitoring and billing options to track consumption?
Networked (Smart) Charging Stations
How are EV manufactures focusing on improving electric vehicles in current models?
Increasing driving range and reducing battery costs
What ordinance in Atlanta requires new public parking facilities to be EV ready?
“EV Ready” Ordinance - # 17-0-1654
What is the typical charging capacity using a DC Fast charger?
15-45 minutes empty to full
What additional costs might be involved in a site assesment?
Service upgrades such as utility distribution line or transformer upgrades
What is the main disadvantage of non-networked EV Charging stations?
Lack of remote monitoring and ability to control usage
What key factor is driving businesses to install EV Charging Stations
Growing consumer awareness and the ability to attract new drivers
What is one key factor to consider regarding the layout of parking spaces for EV Chargers?
Length and width if parking spaces to allow proper cable management and accessibility