Organizing the Project's Scope
Organizing the Project's Team
The Control Account
100

Key words we should search for in a SOW

What are "Shall" and "Will"

100

This document shows Organizational responsibilities of a project

What is an Organizational Breakdown Structure (OBS)?

100
These two elements make up a Control Account and the Control Account's budget is the sum of the budget of these lower-level elements

What are Work Packages and Planning Packages?

200

This is a hierarchical, product-based framework for tasks to be performed on a project

What is a Work Breakdown Structure (WBS)?

200

The Work Breakdown Structure plus the Organizational Breakdown Structure. This document shows WHO is responsible for WHAT on a project.

What is a Responsibility Assignment Matrix (RAM)

200

These elements are necessary for something to be considered a Work Package

What is scope, budget, and duration?

300

A tailored version of the Work Breakdown Structure showing the contractor's interpretation and understanding of the WBS

What is a Contract Work Breakdown Structure (CWBS)

300

This person provides is usually the top of the OBS that everyone reports into.

Who is the Program Manager?

300

The intersection of these two things create a Control Account

What is the WBS and OBS?