Access to inverters and other functional areas was clarified to require this type of access, free and clear of water at all times.
What is vehicular access?
The maximum permitted design voltage drop is this percentage for the DC collection system and this percentage for the AC collection system.
What are 2% DC and 1% AC?
This new plan was added to the deliverables in Section 8.
What is the Construction Traffic Management and Route Layout Plan?
The document naming convention must include these four components.
What are project name, document name, revision number, and submission date?
Testing at 200 W/m² may be used when the preferred irradiance conditions cannot regularly be achieved, but only with approval from this party.
Who is the Owner?
Construction traffic rutting deeper than this range must be leveled and filled before final vegetation work.
What is 2 to 3 inches?
In addition to performing stormwater inspections, the Contractor must now include this form of visual documentation of the inspected items.
What are photos?
All comments from these three engineering drawing stages must be closed before IFC drawings are submitted.
What are the 30%, 60%, and 90% engineering drawings?
Under the updated requirements, an SPCC Plan becomes required once on-site oil storage reaches this capacity.
What is 1,320 gallons?
String I-V curve testing must cover this percentage sample of strings.
What is 10%?
Preventive maintenance must now be completed by personnel holding this qualification.
What is OEM authorization or OEM certification?
Planned underground MV cable splicing is treated this way under the updated requirements.
What is not permitted?
When a design document is “Approved, Proceed, but with comments,” the Contractor has this many business days to revise and resubmit it.
What is 10 business days?
The Civil Deliverables List now requires calculations quantifying impacts to these types of environmental features in acres or square feet.
What are wetlands, ponds, streams, canals, and ditches?
IR scans must be conducted under normal operating conditions at or above this load level, where applicable.
What is 80% load?
Disturbed areas must be restored to this standard, rather than simply being revegetated or remediated.
What is existing conditions or better?
If unplanned damage occurs to an MV cable shorter than this length, the updated requirement calls for the cable to be replaced or rerun in full.
What is 2,500 feet?
When a design document is rejected, the Contractor has this many business days to submit a revised version.
What is 5 business days?
The substation lightning protection study must include these two items showing how the analysis is applied to the design.
What are corresponding drawings and detailed calculations?
The thermographic report must be provided within this many business days.
What is 10 business days?
Under the expanded demolition requirement, the Contractor generally cannot request these three types of relief because an existing obstruction was not shown in the Contract Documents.
What are additional compensation, a change order, and an extension of time?
These conduits are required under roadways, BESS yards, and substations when subject to mechanical damage, unless added protection such as concrete or slurry encasement makes Schedule 40 acceptable.
What is Schedule 80 PVC?
In addition to approval within 30 days, the updated baseline schedule requirements added these three supporting elements.
What are a schedule basis and assumptions narrative, a critical-path narrative, and rules of credit by discipline?
A working plant model is no longer acceptable merely because it functions. It must satisfy the most recent modeling criteria from these four types of entities.
What are the ISO, RTO, TO, and NERC?
This additional MV cable commissioning test must be conducted offline at 60 Hz by an Owner-approved vendor.
What is partial discharge testing, or PD testing?