Daily Cost
Weekly Cost
Monthly Cost
Cost Reporting
Procurement
100

When do timecards need to be submitted for final approval by? 

COB same day operations are completed 

100

When does payroll run?

Mondays 5 PM MST 

100

When is month end close? 

Last Saturday of each month 

100

Where do you pull a short form cost report from?

Launch Pad- Short Form Cost Report 

100

Are Subcontractor/Vendor Tracking sheets optional if you have an alternate tracker?

No

200

How often do you review daily cost and who is responsible for review?

1) Daily 

2) Superintendents responsibility to review and adjust, Engineers to ensure accuracy 

200

When are previous week pay quantities required to be input into the pay estimate for? Day & Time.

Mondays by 12 PM MST

200

When are all items required to be completed in the cost report for Month End by for disciplines? 

Wednesday by 11 AM 

200

What should you reconcile both quantity and cost to when reviewing a cost report? 

Job to Date 

200

Whose responsibility is it to ensure a vendor is paid? 

Field Handler 

If you order/install/buy anything that you have no approved or received an invoice and checked payment for- FOLLOW UP WITH VENDOR

300

What event happens at 2 PM daily? 

Project Daily Cost to all District Executives distributed 

300

Who should be reviewing hours worked report?

Superintendents, Foreman, and Engineers at a minimum 

300

What is an accrual and when do you use it? 

Accrual is a cost placeholder for invoices or committed cost that has not been paid/processed to ensure a capture of what actual costs will hit. It is used for all STS/PMs/SUBs to get accurate job to date costs 

300

What Tag in Control tells you if a WBS is driven off a Pay Item? 

User Def 8


* All Components with driving pay items should align with Forecasted CE AND Final Bid Item Qty

300

When should you initiate a change order? 

Additional Scope, Removal of Scope, prior to overrunning line items.

Vendors should not be billing over current contractual line items or for unawarded scope prior to initiation of a change request. If directed, need a seperate invoice for overrun or additional scope to ensure no hold up in contracted payments

400

How do you calculate a PF and why is PF important? 

1) Earned MHs/Actual MHs 

2) Greater than 1.0 is good, Less than 1.0 is bad. Defines whether you are making or losing money on production.

400

When do action items need to be completed 

Wednesday 10 AM

400

Once completed with all monthly tasks, what is the next step? 

Verify all changes have been incorporated into the cost report 

400

How do you know what makes up a WBS budget?

1) Cost Model

2) Original Estimate

400

How do you see if your contract line items align with your forecasted take off?

Tracking Sheet OR Cost Report WBS 

500

When should you define what budget you have for operations or when budget moves are needed? 

During the development of the workplans

500

What should you come prepared with to the LPR? 

1) Final adjustments of quantities already completed 

2) Hour Moves that were submitted Monday at 12 PM

3) Quantity verification notes with issues/weather/productivity

4) Understanding of Material/STS/Sub costs from previous week

THESE MEETINGS ARE NOT OPTIONAL 

500

What T-Codes in SAP do you use to look up what cost is in a WBS and if a vendor has been paid?

CJI3- WBS Cost Look Up

ZNKIC - Apay for all vendor invoices (Contracts/GEP/Non PO)

500

How do you calculate final forecast cost? 

JTD Cost + (Remaining Qty x Forecast Unit Rate)= Final FC Cost 

Forecast Unit Rate can be based on CE/CB/Manual entry depending on operation or task 

500

What button do you have to press when working in a subcontract tracking sheet? 

Enable Content 