400
1)Name and briefly describe the five phases of implementation presented.
2)Briefly, describe how each of the 5 planning timetables can be used.
3)What are the three major categories of resources that need to be managed during implementation?
What is
1) adoption of program (ensure relevant product), identify/prioritize tasks (timetable), establish system of management (assemble/use resources), putting plans into action (pilot testing/phasing in), and ending or sustaining a program (how long to run a program)
2) basic timeline (put key activities in order), task development (specific times, can use 2 years), Gantt chart (shows planned time frame/when completed), PERT (uses detailed explanation), critical path method (similar to PERT, provides graphs)
3) technical, financial, human