Project Process
Drawing Standards
Contract Documents
Building Code
Construction Materials/Methods
100

This IA document system must be simple, flexible, and consistent across consultants.

What is the IA Drawing Numbering System?

100

What does the code “TI-02” most likely refer to?

What is a wall tile finish?

100

This process begins at the first client meeting and continues throughout the project.

What is Quality Assurance (QA)?

100

This organization publishes model building codes that all IA projects must reference.

What is the International Building Code (IBC)/NFPA?

100

Place to find Detail Library documentation.

What is the IA Technical Resources page

200

This drawing prefix is used for Mechanical (HVAC) plans.

What is the “M” prefix?

200

In a floor plan, which lines should be drawn with the heaviest lineweight to emphasize their importance to the viewer?

What is the exterior perimeter or boundary lines of the building?

200

This phase ensures all drawings and specifications are coordinated, complete, and ready for construction.

What is the Contract Document Phase?

200

This term describes the portion of exit access travel from the most remote point in a room to where occupants have two distinct paths to two exits.

What is Common Path of Egress Travel?

200

This document, submitted by the contractor, shows how they intend to assemble or install materials and must be reviewed to ensure design intent is met.

What are shop drawings?

300

Before sending electronic files to third parties, recipients often must sign this agreement to limit liability and protect IA’s data.

What is an Electronic Media Agreement?

300

When coordinating consultant drawings, what practice ensures that all backgrounds align correctly and avoid overlay mismatches?

What is using a shared project origin?

300

Review of code items like exits, walls, and occupant loads.

What is the Preliminary Review?

300

The most common reason for installing fire-rated partitions in interiors, though not all reasons are code-related.

What is occupancy separation?

300

Tracking these ensures nothing gets lost during construction meetings.

What are submittals and RFIs?

400

Before any design work begins, this document must be executed to define scope, schedule, and terms of service.

What is the IA Contract (or Owner-Architect Agreement)?

400

The blue wall finish tag line indicates as such.

What is Tile and Stone?

400

Ensures furniture, AV, and electrical are coordinated with architecture.

What is Consultant Coordination?

400

Building codes now calculate how many people can be in a room based on this.

What is the room’s use or function?

400

These walls often stop at the ceiling and sometimes need to be extended to full height.

What are partial-height or pony walls?

500

In multi-floor projects, IA drawing sets are typically structured in this hierarchy, starting from general information down to detailed sheets.

What is AN sheets → plan series (by floor) → floor-related sheets → common detail sheets?

500

To maintain drawing accuracy, what is a key item that must be updated every time a sheet is revised and re-issued?

What are the revision cloud and triangle, the revision description in the title block, or the updated issue date?

500

This is the additional charge applied to cover the time spent reviewing drawings, performing QA/QC checks, and preparing specifications.

What is a fee for QA/QC time and specifications?

500

This divides a floor into fire control areas to increase exit capacity in large or collaborative spaces.  

What is a Horizontal Exit?

500

These thinner, lighter steel studs are often proposed to save cost and weight but cannot be used in wet areas or for supporting shelves.

What are EQ studs?

M
e
n
u