200
What is a ‘WBS’ and list the different WBS levels in VISION
A hierarchical outline of the critical work elements of a project that illustrates their relationships to each other and to the project as a whole. The Work Breakdown Structure provides the foundation for programme planning, budget planning and resource allocation. It consists of ‘WBS Elements.’ WBS elements describe tasks or subtasks to be performed within a defined time period. VISION has four levels of WBS Elements: Level 1: Country Programme (CP), Level 2: Outcomes, Level 3: Outputs, Level 4: Activities.