How often should you check your ECPs for checklist feedback?
Daily
When must a launch deviation be replaced?
By the next build phase
ECP
Engineering Change Package
Build Lists freeze when?
The Monday before the build week
What process is required when you receive a late release that is TVN-relevant?
TIK
How many days does a Change Coordinator have to send the ECP checklist after receiving the series NAEL?
7 days (5 business days)
A deviation indicates that a release status is changed for a short, defined period of time or...
...for a specified number of pieces
NRCL (NAEL)
New Release Change List (Neufreigabe-/Aenderungsliste)
What is needed to get a part to NMT if it's missing from the frozen build list?
UPR (Urgent Part Request)
The target for dating non I-step NAELs is?
7 days
What must you set up for "Q" relevant part numbers that change for a pure running change?
Set up Alternate Part Numbers in LTERM Web
This type of deviation must be closed by a single closure NAEL
Text-Only Deviation
TAIS
Technical Administration Information System
When/Why would a UPR get rejected?
-No inventory
-Series part
-etc
When you receive a NAEL with errors, how early can you enter a BDQV for a correction?
Immediately
ECPs should be closed within how many months after it fully implements?
Within 1 month
Which TAIS screen allows you to see other linked NAELs and deviations?
W.I.
PTR
Pulkterminraster (Group Timing Grid)
This BMW derivative requires split-claiming if parts are used in both assembly halls.
G05
What tool can be used to help determine if there are logic (boolean) gaps of corresponding model codes with a new release ?
NERD Report on 6C
If more that 10 cars participating in a Line Trial require post-assembly testing, what process must be utilized?
The PSP Process (Product Sample Process)
The time period to receive a closure/replacement for a series deviation is within 90 days; however, the application period of the closure/replacement is within how many days?
Within 130 calendar days
iPDM
Integrated Product Data Management
What is the first build phase where build lists are no longer used?
AP
Who do you contact to escalate the PO process?
Material Planning
The buyer is not our direct process partner and escalation must go through material planning.