EAC
Metrics
VARs
100

This is a formal assessment of the contract-level Estimate at Completion, typically performed once per year

What is a comprehensive EAC?

100

Dividing BCWS from BCWP gives us what metric?

What is Schedule Performance Index (SPI)?

100
A CAM must write a VAR if this happens

Established thresholds are tripped for the current period or cumulatively

200

This value tells us how efficient the program must be going forward to achieve the EAC

What is the TCPI?

200

Dividing ACWP from BCWP gives us what metric?

What is Cost Performance Index (CPI)?

200

A VAR should address and explain these three things

What is the root cause?

What is the impact to the program?

What is the corrective action?

300

When are IEACs effective and provide a meaningful check?

between 20% and 80% of project completion, during the core execution phase.

300

(BAC - BCWP) / (EAC - ACWP) equals what metric?

To Complete Performance Index (TCPI)

300

This document should be printed and hanging in your office next to your computer instead of a photo of your family

What is the Earned Value Management Gold Card?