A person directly involved in line breaking operations by either performing work or authoring work to be performed.
What is an Authorized Person?
100
Marks the exact location of the Line Break by painting or tagging.
What is the Owning Department?
100
Appendix D
What is the Line Breaking PPE Table?
100
Completed in the field WITH crafts persons and equipment owners present
What is the Line Breaking permit?
200
Recognizes where line breaking is taking place and maintains a safe distance.
What is an Affected Employee/Contractor?
200
May be necessary to determine if internal configuration (baffles, standpipes, packing, etc) may prevent complete drainage of materials.
What are drawings?
200
Escalate the lack of secondary isolation to perform a feasibility study for installation
What is Engineering?
200
Issued no more than two (2) hours prior to the first line break.
What is a Line Break permit?
300
Participates in pre-job discussion and he completion of Line Breaking permit.
What is an Owning Department (Process Owner)?
300
This person traces the equipment to verify that all potential energy sources have been identified and isolated according to the sites procedure for LTT.
What is a Permit Issuer?
300
Ensures the suitable containers/resources are available to collect and properly dispose of process materials.
What is the Process Owner?
400
Provides technical guidance to ensure effective training.
What is a HSE Leader?
400
A line break containing check valves and an isolation device where liquid/pressure cannot be safely bled.
What is a First Break?
400
Tested for function prior to work and less than 10 seconds from work area
What is a Safety Eye/Face/Shower?
400
<5% Lower Explosive Limit (LEL).
What reading is required as a permit condition when monitoring is required for lines in flammable or combustible service?
500
Maintains a safe distance from Line Break or wears PPE.