Isolation Types
Hierarchy of Controls
Bleed Points
De-Isolation
Stones Specific
100

What is a boundary isolation?

Boundary isolations are isolations used for an entire platform, skid, or vessel. It typically requires the platform or vessel to be pressure free’d and drained in order to meet the isolation hierarchy of controls

100

What tools do you use to determine your isolation requirements? 

Hierarchy of Controls, Hazard Factor Spreadsheet, and the Short Duration Job Risk Assessment

100

Are bleed points required to be part of the lockout?

Yes, required to be listed. Also required to hang a open bleed tag on any open bleed valves

100

What does DFT mean?

De-isolate for testing

100

Where are lock boxes checked out from? 

Maintenance supervisor's office

200

What is the criteria for using operational control as an isolation method?

Operational Control:

  • Single craft work only
  • Line of Sight to all isolation points entire time
  • Maximum 3-point isolation
  • Maximum 1 hr. work duration
  • No unrefined hydrocarbons (unless approved/vetted by leadership)
200

What is an operational control type isolation?

Operational control applies to low risk, short-duration routine operations. You must stay within eyesight of isolation points while the work is in progress. Some examples of operational control type isolations are flushing bridles and BSEE testing.

200

Can you walk away from an active bleed point?

No, PSF #2

Do Not leave an open drain or critical transfer unattended

200

What is required if the personal isolation job goes longer than 14 hours?

The team lead should be notified, and a LOTO certificate should be entered.

200

Who is the isolation verifier/isolation authorizer?

Team Leader or Supervisor

300

What is a positive isolation?

Either remove a spool piece or install a spectacle blind/swing a spade

300

What valves can be used for isolation and what valves cannot be used?

Cannot be used-check valves, flow control valves

300

Do you have to put a bleed point in the manipulated valve register?

Yes, if:

It is not listed in the LOTO certificate or in the procedure

300

What is the max amount of time operational control can be used as isolation?

1 hour

300

What type of isolation is required for a level 3 CSE?

A positive isolation is required (air gap)

400

What is the criteria for using a personal isolation?

What is the criteria for using a personal isolation?

Personal Isolation:

  • Multi-craft allowed with corresponding signatures on JSA stating they reviewed and personal lock installed
  • Group LOTO form required if group LOTO is used
  • 14 hour duration maximum (single shift)

10 point isolation maximum – (Not applicable if inclusive procedure is used)

400

What is the hierarchy of controls?

First Step: Air gap equipment. If you can’t air gap, then

Second: Isolate equipment with blinds or other physical barriers. If you can’t do that, then

Third: Double block and bleed or single valve with one additional barrier, ie PPE

400

What is PSF #8?

Always check that equipment is pressure free and drained, and provides safe isolation before starting maintenance work

400

What documentation is required on the work site if a group LOTO is used instead of individual locks?

The Group lock form needs to be completed and kept within the work group’s documentation

400

How many people minimum are required for tank entries?

Two people

500

What are the requirements for when you use a LOTO certificate?

LOTO Certificate:

  • Utilized if Operational Control/ Personal Isolation cannot be applied
500

What do you do if you can’t meet the Hierarchy of Controls (ie double block & bleed)?

  • Use the Hazard Factor Calculation spreadsheet to determine the minimum isolation requirements
  • Use the Isolation Decision Tree to decide your next step-ie what to do if you can’t meet the minimum isolation
  • Check if the short job duration risk assessment applies

If a risk assessment is required, contact team lead

500

When performing Subsea LOTO’s, what devices are acceptable instead of a typical lock, chain, or plastic cover?

  • Override tool (with photo verification)
  • Parking frame (with photo verification)
  • Password protected disabled valve (with photo verification)
  • Torque tool (with photos to verify that torque tool was calibrated, the torque applied, and valve position)
  • Photo of a positive isolation completed remotely
500

What is the process if you need to de-isolate for testing?

  • Each member of group removes their lock from the lockbox
  • Supervisor approves de-isolate for testing
  • Supervisor initials each point on the LOTO certificate that needs to deisolated for testing
  • Isolation owner will remove locks from DFT points and initial
  • Testing is execute

If test is passed, remove isolation. If test is failed, re-apply isolation.

500

What information is required in your contingency plans that are part of the LOTO?

Methods of responding to leakage.

Identification of additional isolation valves and the intended actions in the event of isolation failure.

Identification of the location of Emergency Shutdown (ESD) or Unit Stop buttons.

Establishment of contact with the control room or location leadership prior to the initial breaking of containment.

The release/leak response plan shall be followed if a leak or release develops.

Any safety devices/ gear (i.e. Safety Showers, Fire Extinguishers, Eye Wash Stations, etc…) needed for the task or response plan shall be documented here.