Name a document that needs to be done weekly.
Job Site Inspection
If formwork fails, is it an OSHA/LNI violation?
Yes. Formwork must be capable of supporting, without failure: vertical loads and Lateral loads
How many pounds of force does a guardrail need to be able withstand?
200 LBS
If a space has no identified hazards, what kind of space would it be defined as?
Non permit, Alternative Method Entry
Place these in the proper order of the hierarchy of controls:
Administrative
PPE
Engineering
Engineering
Administrative
PPE
What does JHA stand for?
Job Hazard Analysis
What should you reference when you are planning to cut, grind or chip concrete?
Table 1
What grade 2x4 is MCC allowed to use for Guardrail?
1
Name 2 of 3 types of confined spaces according to OSHA regulations.
Non Permit, Permit, Alternate Entry
Which 2 violation types can cost the most?
Willful, Repeated - Minimum $11,524 and maximum $161,323
How much time do you have to report a death to OSHA or LNI?
8 Hours
What are some criteria that would make ellis shores unusable?
Rot, 4x4s are split throughout, excessive damage.
Outside of every time we use them, how often are we required to inspect our fall protection equipment?
Every year
How often do you have to be trained in confined space?
Annually
How many years are looked at to calculate a company's EMR?
The previous 3 years
Name 1 item that needs to be reported to OSHA or LNI within 24 hours.
Hospitalization, Amputation, Loss of an eye
What does PEL stand for?
Permissible Exposure Limit
How far are you allowed to free fall in a Personal Fall Arrest System?
6 Feet
Give 3 reasons a confined space would be considered a permit required confined space.
Electrical hazard, atmospheric hazard, fall hazard, engulfment hazard, entrapment hazard, other recognized safety hazard.
How is an incident rate calculated?
Number of injuries x 200,000/Employee hours worked
After an OSHA/LNI inspection, how long does the agency have to close the inspection(give the citation)?
6 Months
What is the action level for Silica?
25 Micrograms per cubic meter
If an anchor point is engineered, how much does it need to hold?
2 times the maximum intended load.
Name all 3 criteria that make up a confined space
Large enough to enter, Limited access and egress, Not intended for continuous occupancy.
How far away can scaffolding be from a wall?
18 inches