I Know That
Can We Do That?
100
What should the default task mode be set to?
Auto Scheduled. And how is it done?
100
Name 2 ways you can show the WBS Codes in a full schedule?
1. Add the WBS column 2. Format Tab > Outline Number
200
Which way should tasks progress in your Gantt chart? How can you move the tasks after the schedule is created?
1. From top left to bottom right. 2. Click and Highlight > Click the ID and Move
200
What is the closest way to see a visual representation of the WBS within Microsoft Project Professional?
Use the Network Diagram View.
300
What other lead/lag can be used besides standard date and time?
Percentages.
300
What is the BEST way to get a visual representation of the project's milestones into the Project Site?
Use the deliverables feature.
400
What is the BEST way to visually show deadlines are 'On Track or Behind' in a schedule without using date constraints?
Using the deadline task feature.
400
Name at least 3 ways to identify the Critical Path. **Bonus 300** Which is the "Best" gantt view for seeing the critical path?
Most all views can: - Highlight - Filters - Grouping
500
How can you modify your schedules views and columns and save it to open it later in the same format?
Magic ; )
500
How can a project that is 50% complete have a CPI and SPI of 0?
The project has NOT been baselined.
Continue
ESC
Reveal Correct Response
Spacebar
M
e
n
u
Team 1
0
+
-
Microsoft Project Server - Schedule Management
No teams
1 team
2 teams
3 teams
4 teams
5 teams
6 teams
7 teams
8 teams
9 teams
10 teams
Custom
Press
F11
Select menu option
View > Enter Fullscreen
for full-screen mode
Edit
•
Print
•
Download
•
Embed
•
Share
JeopardyLabs