What distinguishes an EZ form from an full AFE?
$50,000 project value mark
What does the "64-22" denotion stand for in asphalt product names?
the "64" represents the 7 -day average maximum pavement temperature, in degrees Celsius, for which this binder can be used. The second number, "-22," signifies the single day minimum temperature, in degrees Celsius, for which the binder can be used without the likelihood of failure.
This item sends signal waves into the tanks to determine product level
radar gauge
When writing a requisition in SAP which category will you enter the dollar amount?
quantity
What is the company code for Ergon Asphalt and emulsion & Ergon Asphalt partners?
(165/175)
the first step after receiving a project number is to create what & where?
create a project folder - J drive
Whats required to make Emulsion
asphalt and soap
What piece of equipment heats water into steam
boiler
When writing a requisition who is the recipient?
Plant manager
What is the initial phase of a project called?
FEL / scope & development
when searching for existing specs to send to contractors use this?
policy tech
define the quantity that measures the magnitude of internal friction / resistance in flow i.e. Thickness
viscosity
What is the best piping material for acid applications?
CPVC piping, not metals
When populating the header text in a requisition who is that information for?
procurement
P&ID stands for what?
piping and instrumentation diagram
Where to you go to comment updates on projects?
smartsheets
What type of pump would we use in an asphalt application?
pd pump -> gear pump
What are the four methods/ mediums we heat product with?
electric, hot oil, steam, water
What is the term that allows us to attach work orders to a piece of equipment?
(functional location)
What type of schedule layout is used to display project timeline?
gantt chart
What is the 3 digit number that designates engineering drawings on the R drive
099
What element is needed to react polymer and asphalt
sulfur
What are the two main pump types & the main difference?
Dynamic/ Kinetic & positive displacement
What 3 digit WBS code is used for "tanks"
- 800
You cannot close a project out until this column in the budget summary is cleared out?
Commitments