Simple Tingz
Procurement of Work
Framework Agreement
Contract Management
100

What is the primary output of the Evaluation Committee in a GOJ procurement process?

A detailed evaluation report

100

What is the estimated economic impact of public procurement on Jamaica's Gross Domestic Product (GDP)?

30%

100

What is identified as a 'Pass/Fail' criterion in the Evaluation Framework?

Financial and Compliance

100

Which pillar of contract oversight is specifically concerned with protecting the Municipal Corporation from litigation?

Legal Risk

200

In what year did the Public Procurement Act came in effect  name to 2 years they were admended.

Public Procurement Act 2015

Public Procurement Amended 2018

Public Procurement Amended 2025

200

Define works procurement?

means the carrying out of any of the following activities, namely, construction, reconstruction, assembly, altering, manufacturing, processing, fabrication, erection, instrumentation, installation, fitting out, improvement, commissioning, demolition, maintenance, repair and renovation involved with building, civil engineering, structural engineering, electrical engineering, mechanical engineering and other engineering and technology projects;

200

What are the types of Framework Agreements?

Open and Close

200

What does CCEP stands for ?

Contract Consultant Evaluation Program

300

Name the current threshold , what they were before including the tiers of approval

below 30 ------> up (60) million Head of Entity

30 million  ------> between 60 and (100) Millions PPC 

above 60 millions ----> above 100 millions

300

Name 2 benefits of a site vist?

Visual Assessment: Contractors can view the actual site, understand physical constraints, and assess logistical needs.

Accurate Costing: Helps determine necessary resources, labor, and materials, leading to more realistic pricing.

Identifying Challenges: Physical inspection allows for identifying potential on-site challenges not visible in documents.

Confirming Scope: Confirms what work is required and the existing site conditions.

300

List 4 reasons for establishing a Framework Agreement.

There is frequent re-ordering based on the same (or similar) set of specifications;

The volume required cannot be precisely predicted;

The required delivery dates cannot be precisely predicted;

Independent buying units within a Ministry or between different Ministries are acquiring the same supplies;

Aggregating the demand from buying units will lead to significant volume discounts;

Small buying units lack the capacity to arrange and manage their contracts

Crisis planning cannot accommodate the time required for traditional processes;

No single supplier is considered to have sufficient capacity;

A choice of suppliers is considered desirable;

A wide range of suppliers is available; and

Price and/or performance of the works, goods or services delivered is measured by well established standards.

300

What is the function of the Technical Officer during the 'Certification' step of the payment flow?

Signing off the Interim Payment Certificate

400

A procuring entity is planning a 'Works' project estimated at JMD $100 million. Under the GOJ framework, what is the required level of competition?

Open National Competition

400

Name the 2 evaluation Criteria

Lowest Cost

Most advantageous

400

Define Open Framework Agreement.

Means a framework agreement in which a contractor who, at the time of the making of the agreement, was not a party to it and is able by the terms of the agreement to subsequently becoming party.

400

When managing variations, what must be calculated to determine if PPC (Public Procurement Commission) approval is required?

The cumulative variation percentage the original contract sum

500

Name 5 administrative Guidance issued by the Office and where can you fine them?

Guidance Note 1/2020 (GN1/20) – Criteria for the Award of Contracts

Guidance Note 2/2023 (GN2/23) – Contractor and Consultant Performance Evaluation

Guidance Note 1/2021 (GN1/21) – Procurement Under Alternative Systems

Guidance Note 3/2023 (GN3/23) – Public Procurement Committee Guidance Note

Guidance Note – Role of Boards in Public Procurement

Guidance Note 2/2022 (GN2/22) – Use of Electronic Procurement in GOJ Procurement Operations

Guidance Note 1/2022 (GN1/22) – Submission of Procurement Reporting System (PRS) Reports

Guidance Note 2/2025 (GN2/25) – Procurement in Situations of Emergency or Extreme Urgency

Guidance Note 1/2023 (GN1/23) – Contracts for Security Guard Services

Value for Money Procurement Standard – December 31, 2024

500

Name 2 benefits of the pre-bid meeting?

Key Benefits of Pre-Bid Meetings:

Clarification of Scope: Potential bidders gain direct clarification on tender documents, specifications, and requirements.

Reduced Risk and Errors: Identifying ambiguities early minimizes costly mistakes in the bid.

Competitive Advantage: Allows bidders to ask questions, understand the owner's priorities.

Compliance: Ensures all participants understand mandatory requirements, reducing the risk of non-compliant, rejected bids.

500

Define Closed Framework Agreement/

Closed Framework Agreement: means a framework agreement in which a contractor who, at the time of the making of the agreement, was not a party to it and is excluded by the terms of the agreement from subsequently becoming party.

500

What is the purpose of a contract management plan?

To outline how contract performance will be monitored and controlled

M
e
n
u