Who is authorized to be under the load?

Only riggers handling the load.

100

A ___ is set to give the operator sufficient warning to prevent encroachment.  

Proximity alarm. 

100

What is not required as part of inspecting wire rope as per OSHA?

Untwisting and booming down.

100

When is it acceptable to use cell phone at work site?

In signaling a crane.  

100

Personnel platform work stops when wind exceeds ____.

20 mph.

200

How often does OSHA require a written wire rope inspection?

Once a month.

200

The employer must assume that all power lines are _____ unless the utility owner/operator confirms otherwise.   

energized.  

200

A diameter reduction of more then ____ % from nominal diameter falls under apparent deficiencies.

5%.  

200

Before starting the engine, the operator must….

Verify that all controls are in the proper starting position and personnel are in the clear.  

200

What percentage of tipping do crawler cranes use?

75%.  

300

Who ensures ground preparations meet requirements?

The controlling entity.

300

Once you have determined how close you can get to power lines, you must erect ________?

An elevated warning line, barricade or sign.

300

How many broken wires are allowed in one rope lay of standing wire rope beyond the rope capacity? 

2.  
300

Traveling with a load is prohibited, if….

The practice is prohibited by the manufacturer. 

300

Repetitive pick up points refer to ____, when rope is being used on a single layer and being spooled repetitively on a drum. 

Duty cycle operations. 

400

When pendent lines are in tension, which pin can be removed?

None.

400

According to 1926.1409, while disassembling a crane a distance of ______ ft must be substituted for 20ft wherever specified for power lines at or below 1000kV?

50 ft. 

400

If a rope is shortened, the employer must…..

Ensure drum will have two wraps left when load landed or boom is in its lowest position.  

400

Irrespective of who gives it, the operator must…..

Obey a stop signal or emergency signal.  

400

What shuts off power to those equipment functions which can increase the severity of loading on equipment?

Load moment limiter.   

500

When using employer procedures for assembling cranes, what must they fist ensure?

The prevention of dangerous movement.  

500

What is the minimum distance between a boom and power line with 600kV?

35 ft.

500

Prior to cutting wire rope, ____ must be placed on each side of the point to be cut.

Seizing.  

500

What must be done when using non-standardized hand signals?

The signal person, operator, and lift director must contact each other prior to the operation and agree on what is to be used.   

500

As per OSHA 1926.1412(F)(2) at least every 12 months equipment must be inspected.  What must be inspected?   