Osha
Volt
Tech
Site
Wire Rope
100

1926.1404(r)(1) states that all rigging work must be done by who?

A Qualified rigger

100

For power lines at or below 1000kV. What is the specific distance to be a safe working distance away?

45 feet

100

A      must being a visual inspection prior to each shift the equipment will be used

Competent person

100

       - means the ability of the ground to support the equipment 

Ground conditions 

100

   - randomly distributed broken wires in 30 rope diameters

4

200

According to1926.1405(a) when can none of the pins in the pendants are to be removed?

When pendants are in tension

200

What must be done by the utility owner/operator in order to have crane actively working in area closer than the allowable distance?

Deenergized and grounded 

200

Inspection on     for deformation, cracks, excessive wear, etc….

Rigging hardware 

200

        - must insure ground preparations necessary to meet requirements 

Control entity 

200

   - randomly distributed broken wires in six rope diameters

2

300

1926.1408(f)(2) states if tag lines to be used, they must be what?

Non-conductive 

300

What must be held before employees work in an area near power lines?

Meeting

300

Every 12 months the equipment must be inspected by a qualified person 

Annual inspections

300

       - determine the ground to see if it’s proper to build crane over

A.D director

300

   - randomly distributed broken wires in one rope lay

6

400

1926.1404(f)(1)- When _____ are being remove, employees must not be under the boom

Pins

400

Who is responsible to confirm that power lines have been, and continues to be, deenergized and visibly grounded at the worksite?

Utility owner/operator

400

Equipment idle for 3 months or more to be inspected by qualified person

Monthly inspections 

400

If no controlling entity present…who is responsible 

Employer that has authority over site

400

The inspection must consist of observation of wire ropes

Running and Standing

500

1926.1404(h)(5)- When attaching rigging to a boom, the rigging must be suitable for ______ and facilitating safe handling of these components 

Preventing structural damage 

500

At over 500 to 750kV.. how many feet away is considered a safe working area?

35 feet

500

Tire in use, inspection for proper……

Inflation and good condition 

500

 - means blocking,mats to in like (marshes,wetlands)

Supporting materials

500

Wire rope structure such as kinking, crushing, unstranding or signs of core failure

Significant distortion 