This abbreviation stands for the quality assurance process governing an employee's authorized scope for engineering practices.
What is EJAA (Engineering Job Approval Authority)?
Texas NRCS policy enforces this hard restriction regarding the delegation of engineering authority to non-NRCS employees.
What is that non-NRCS employees shall not be delegated engineering authority?
For Class I and II engineering jobs in Texas, this specific type of technical verification must be performed by someone other than the designer.
What is a computational check?
This specific number must be physically called by a contractor to initiate an underground utility location request in the field.
What is 811?
Under the Texas planning guidelines, appropriate engineering job approval authority is defined as any delegated design authority that is not designated as this word.
What is "None"?
This federal rule framework dictates how Value Engineering Change Proposals are handled in Texas NRCS Federal contracts.
What is the FAR (Federal Acquisition Regulation)?
For individuals in their present position for less than 3 years, their engineering job approval authority must be reviewed and updated at this frequency.
What is annually?
To act as the official design reviewer for a Class III or Class IV job, an employee must possess this level of EJAA.
What is an EJAA level equal to or greater than the job class being reviewed?
Due to severe liability risks, NRCS personnel are strictly forbidden from providing these to a cooperator or contractor for utility location requests.
What are GPS (or GNSS) coordinates?
This administrative item must be prepared for all project work and all designs submitted to the State Office staff for review, regardless of the EJAA category.
What is a design folder and design report?
This state agency manages Texas dam safety regulations and collaborates with the NRCS on formal inspections via a memorandum of understanding.
What is the TCEQ (Texas Commission on Environmental Quality)?
This official retains the ultimate delegated engineering job approval authority for all engineering work carried out within the state of Texas.
Who is the State Conservation Engineer (SCE)?
A Class V design review in Texas must be completed and documented by an individual holding this specific credential.
What is a Professional Engineer (PE) licensed in Texas?
This administrative action can occur if a cooperator fails to submit Form TX-ENG-80B.
What is the termination of NRCS assistance for the practice?
All requests originating from field personnel seeking a State Office design review must be routed through this intermediate official.
Who is the Zone Engineer?
This core national policy dictates that all engineering work performed by or for the NRCS must conform to this manual.
What is the National Engineering Manual (NEM)?
This is the maximum design approval job class that can generally be delegated to a non-licensed NRCS engineer.
What is Class IV?
Class VI designs must be submitted directly to this individual or their designee for formal technical review prior to approval.
Who is the State Conservation Engineer (SCE)?
This critical engineering milestone must not begin until Form TX-ENG-80B has been completed, returned, signed, and dated by an NRCS employee.
What is final construction staking of the practice?
Policy mandates that this single component determines the overall engineering job classification when analyzing multiple design criteria.
What is the highest category of any single most-limiting factor?
This type of data can only be used for practice design when procedures in a specific National Instruction are followed.
Light Detection and Ranging (LiDAR) Data
- Reference: TXNEM 540.3
An employee must have this level or higher of design EJAA in order for it to remain in effect during the 6-month transition period after transferring to another Zone within Texas.
What is EJAA job class II.
- Reference: TXNEM 501.4 B 9
National policy dictates that a Class VIII job cannot be approved by the State Conservation Engineer without the prior technical review and concurrence of this official.
Who is the Director of the Conservation Engineering Division (CED)?
This safety directive must be followed immediately by all NRCS personnel if a dangerous utility is struck or ruptured during active construction operations.
What is to immediately evacuate the area?
All engineering designs can be divided into these 3 design stages.
Data Collection & Evaluation, Preliminary Design, and Final Design
- Reference: NEM 511.2