Which part of the ORM step process, involves identifying control options and effects?
What is make risk decisions?
100
Accepting unnecessary risk is one of the four ORM principles?
What is false? No one should accept unnecessary risk.
100
What are the three levels of ORM?
In-depth, Deliberate, Time Critical
100
What process is a decision making tool used by Navy personnel at all levels, to increase operational effectiveness by identifying, assessing, and managing risk.
What is ORM?
100
When making risk decisions we Identify Control Options, what is a Physical Control?
These controls take the form of barriers to and guards against a hazard, such as: personal protective equipment (PPE), fences, or special oversight personnel.
200
Which step of the ORM process, establishes accountability and provides support and clearly identifies how to implement?
What is Implement Controls?
200
The CO or civilian equivalent will be
designated as the command ORM manager.
What is false? (XO)
200
The _______ level refers to situations when there is ample time to apply the RM process to the detailed planning of a mission or task.
Deliberate
200
The risk when measured versus the benefit or value of the mission or task that cannot be tolerated and must be eliminated or controlled.
What is Unacceptable Risk?
200
Step 2. Assess the Hazards, assessing the severity of the hazards is categorized in to how many categories?
What is 4.
300
Analyzing the mission, list hazards and determine root causes, are part of which ORM step of the ORM cycle?
What is identify hazards?
300
ORM is a process only to be applied to on-duty mission or tasks.
False
300
The ______ level refers to situations when time is not a limiting factor and the right answer is required for a successful mission or task.
In-depth
300
An unplanned event or series of events resulting in death, injury, occupational illness; damage to or loss of equipment or property; or damage to the environment.
What is a Mishap?
300
Little or no adverse impact on mission capability or unit readiness. Minimal threat to personnel, safety, or health. Slight equipment or systems damage, but fully functional and serviceable. Little or no property or environmental damage. What category of severity?
Category 4.
400
Which step of the ORM process includes assessing severity and probability?
What is assess hazards?
400
The amount of risk the Navy will accept in war is much greater than what the Navy should accept in peace, but the process is the same.
True
400
Time is limited in this situation, so the application of the 5-step process has proven impractical and ineffective. The Navy has adopted the ABCD Model, to facilitate use of risk management at the __________ level
Time Critical
400
The portion of identified risk that is allowed to persist during the mission or task.
What is Acceptable Risk?
400
How many basic principles make up ORM.
4. Accept Risk when Benefits Outweigh the Cost, Accept No Unnecessary Risk, Anticipate and Manage Risk by Planning, Make Risk Decisions at the Right Level
500
Which step of the ORM process includes monitoring, reviewing and providing feedback?
What is supervise?
500
OPNAVINST 3600.39 (Series) is the overall instruction on NAVY ORM management.
What is False? -OPNAVINST 3500.39 (Series)
500
What is the model the NAVY has adopted to facilitate use of RM at the time critical level.
A- Assess the situation
B- Balance the resources
C- Communicate to others
D- Do and Debrief the event
500
Actions taken or measures put in place to eliminate a hazard or reduce the associated identified risk.
What is a control?
500
ORM model manager.
Who is Commander, Naval Safety Center (NAVSAFECEN)