Roles and Responsibilities
Hazards
Partial obstruction
Full blockage
Famous movie quotes
100

Contact Facility Integrity Group (FIG) and make them aware of the current situation.

Shift Lead

100

Known to cause a sudden release of the obstruction 

High differential pressure

100

While conducting pressure survey you should always assume there is multiple what

Obstructions

100

When dealing with ice plugs who should be notified before putting line back into service 

FIG

100

You can't handle the truth

A few good men

200

Initiate operational corrective actions to prevent serious injury or damage to pipelines and equipment.  This corrective action, may include shutdown of equipment, pipelines.

Control room operator

200

This hazard is known to cause hearing loss and workers can be exposed to this while equalizing pressures across blockages

High noise levels

200

Where damage is most likely to occur if obstruction breaks free 

control valves, closed valves or elbows

200

What is used to test for disintegration/melting of full blockages 

Predefined medium (Nitrogen)

200

I'll be back

Terminator 

300

Protect yourself first, never attempt to treat a hydrate formation or ice plug without thoroughly understanding every aspect of this operating procedure.

Unit Operator

300

Which explosive, toxic or hazardous gases and vapors may be present when dealing with hydrates/ice plugs

H2S/LEL/BENZENE

300

On what side of the obstruction should methanol be injected for a partial obstruction

Upstream


Full obstructions should have methanol injected on the upstream and downstream side.

300

Where are ice plugs most likely to be found

Low point of the line

300

"I'm not quite sure how to put this, but... I'm kind of a big deal"

Anchorman

400

Ensure the pipeline system is fully reinstated before being placed back into service.  (chemical injection systems removed, insulation, cladding reinstated)

Unit Operator

400

These external pressure sources are other hazards associated with hydrate/ice plug handling 

Baker Pump/Pressure Truck

400

When it is determined the partial obstruction is cleared you should

return piping to original service

400

When dealing with full blockage - gas hydrate we equalize pressure across the blockage  by slowly depressurizing the high pressure side in 10% increments. When dealing with an ice plug what pressure is desired on both sides of the plug

Atmospheric


ensure there is no significant differential pressure as this will give energy to move plug. (No more than 10%)

400

"You're gonna need a bigger boat"

Jaws

500

Complete pipeline integrity evaluations and assessments on the affected pipeline system.

FIG

500

Equipment exposed to a temperature below the ______ _______ ______ _____ is at risk of a brittle fracture 

minimum design metal temperature 

500

When dealing with a gas hydrate-full blockage we inject methanol or Mikes De-icer. What is applied to an ice plug to break down the obstruction.

Heat 

Heat should not be applied to a pipe section unless the melting liquids can be removed during the melting process ie. Open drain. Thermal expansion of liquids during heating results in dangerously high pressure that can fail the pipe material 


500

I award you no points, and may god have mercy on your sould

Billy Madison