Project Cycle
Project Design
Monitoring & Evaluation
100

What are the some of the six main stages of the project cycle? (mention 3)

Identification; preparation and design; appraisal; approval and financing; implementation and monitoring; completion and evaluation.

100

What does DMF stand for?

Design and Monitoring Framework.


100

What is the difference between monitoring and evaluation?

Monitoring continuously tracks progress and indicators. Evaluation assesses the project's design, implementation, results, and lessons learned.

200

What is the purpose of a Country Partnership Strategy (CPS)?

To identify a country's development challenges and priorities and guide where development assistance should focus.

200

What is the difference between an output and an outcome?

An output is a good or service delivered by the project; an outcome is the immediate result or change the project intends to achieve.

200

What does sustainability mean in project evaluation?

Whether the project's benefits are likely to continue after the intervention ends.

300

What is the main purpose of project appraisal?

To examine the project's viability, risks, expected results, institutional capacity, and readiness for implementation.

300

What is a problem tree, and why is it used?

It maps a central problem, its causes, and its effects to help the team understand the situation before choosing solutions.

300

What is an indicator, and why is it important?

A measurable variable used to track performance or results and assess progress toward a target.

400

What are two important factors that must be considered before a development project is approved?

Possible answers include technical and financial viability, institutional capacity, environmental and social impacts, risks, policy compatibility, and sustainability.

400

What are assumptions and risks in a DMF?

Assumptions are conditions needed for the results chain to work; risks are factors that could prevent or undermine the intended results.

400

What is the difference between ex-ante and ex-post evaluation?

Ex-ante evaluation takes place before implementation; ex-post evaluation examines results after time has passed.

500

Why is project completion more than finishing activities and spending the budget?

It documents actual results, assesses performance, records lessons, and identifies measures needed to sustain benefits.

500

Explain the logical relationship between inputs, activities, outputs, outcomes, and impact.

Inputs are resources used for activities; activities produce outputs; outputs contribute to outcomes; outcomes contribute to broader development impact.

500

A project delivers infrastructure, but the community cannot maintain it. Which evaluation criterion is most directly affected, and why?

Sustainability, because the benefits may not continue after project completion.