Product Overview
Design/Planning
Site Readiness
Delivery/Install
100

The THREE IGS 7 configurations available

What is Standard, Operating Room (OR) and Hybrid Operating Room (HOR)?

100

The maximum USEABLE cable length running from the CMS to the technical room

What is 42ft/13m?

100

Responsible for designing the CMS support structure above the ceiling.

Who is the customer/hospital?

100

Used to protect the IGS7 floor during the delivery/installation process?

What is MDF (Medium Density Fiberboard)?

200

The Interact Discovery RT is a combination of these TWO systems.

What are an IGS 530/540 and a CT Discovery RT system?

200

Distance the CMS/customer plate should be offset from the table longitudinal axis.

What is 570mm?
200

Must be operational prior to IGS7 floor application?

HVAC/Air conditioning

200

The number of reflectors/targets to install within the IGS7 room.

What is 11 reflectors/targets?

BONUS 200 points:

What are the minimum & maximum heights?

300

The minimum back-out clearance distance for IGS IR/HOR.

What is 20in/500mm?

300

Request this when encountering a laminar flow ceiling in your IGS room.

What is a reflected ceiling plan (RCP)?

300

The number of CMS plate mounting heights.

What is 4 different heights?

BONUS 300 points:

What are those 4 different heights?

300

Recommended installation location for the video input box (V-point).

What is a wall mount?

400

The definition of RIRP.

What is Room Interventional Reference Point?

This is the gantry iso-center when the gantry is in the head position.

400

Two items to consider when placing CMS location in a room drawing.

What are:

1) the table pivot pint/iso-center?

2) the distance to technical/equipment room?

400

The IGS 7 floor curation time prior to installing floor protection.

What is 3 days/72 hours?

400

A cable linking the video output from imaging device to the input of the LDM controller.

What is a link-set?

500

The 3 tilting patient tables available with the Discovery IGS system.

What are the Innova IQ for interventional, the Innova IQ OR table for surgical and the Magnus Maquet OR table for surgical

BONUS 500 points: What is the patient weight limit for the Innova tables?

500

The reason for NOT installing a flush floor duct in the IGS7 room.

What are:

1) hygiene issues?

2) potential cracking of the monopur floor?

500

The general Invasive site requirements (high level needs).

What are:

1) Standard NEMA 5-20R, 120v plugs

2) Connection to separate/dedicated 15Amp circuit

3) 1 network drop and 1 IP address

4) Cables to be pulled: 2 Amplifier Fiber Optic Cables, Ablation Serial Cable, 1-2 Video/Power monitor cables, Stimulator cable, PDM Cat 5 cable (sometimes)

500

Common CMS installation issues.

What are:

1) CMS plate at wrong height?

2) Ceiling obstructions interfering with CMS cable guide?

3) CMS plate installed rotate 90o?

M
e
n